(A) A permittee may apply to the Director for an exemption under this section when the construction is necessary in the public interest or to provide a public service.
(B) By way of example, but not by limitation, an exemption could be requested in order to provide services to a part of the town where no service would be available without construction.
(C) If a non-emergency exemption is granted to disturb a public way within the three-year period, the Director may, in his or her sole discretion, impose additional restoration requirements, including, but not necessarily limited to, repaving of a larger area, such as an entire block in which the construction occurs.
(Prior Code, § 165.18.4) (Ord. 503, passed 7-7-2005; Ord. 577, passed 11-6-2014)
The streets shall be restored and repaired in accordance with design and construction standards adopted the town and guaranteed in accordance with § 156.011 of this chapter.
(Prior Code, § 165.18.5) (Ord. 503, passed 7-7-2005; Ord. 577, passed 11-6-2014)
RIGHT-OF-WAY PERMIT FEES
(A) The formula for degradation costs is provided in Table 1 – 30-year design standard. Table 2 illustrates a hypothetical calculation.
(1) Table 1: Cost of recovery method (30-year street design standard)
Cost of Recovery Method (30-Year Street Design Standard)
| |||||||
Cost per square yard for streets, overlays and sealcoats X depreciation rate X area of influence (1) | |||||||
Depreciation Rates
|
Cost Per Square Yard (3)
| ||||||
Street (2) |
Overlays | Type | Cost | ||||
Age | Rate | Age | Rate | Age | Rate | Asphalt reconstruction | $45
|
Cost of Recovery Method (30-Year Street Design Standard)
| |||||||
(1) Area of influence is equal to area of the cut plus 3 feet on each side (expressed in square yards) (2) Depreciation rates are based on a 30-year street design standard. Depreciation for the first 5 years is 1% per year, followed by straight line depreciation less 15% for the remaining street design standard (25 years). (3) Depreciation can occur at 1% per year after this time for up to 15 years or street reconstruction, whichever occurs first. |
(2) Table 2: Recommended cost of recovery method.
Recommended Cost of Recovery Method | ||||
Cost per square yard for streets, overlays and sealcoats X depreciation rate X area of influence (1) | ||||
Example | ||||
Assumptions: Street is 16 years old Overlay is 5 years old Sealcoat is 1 year old Area of cut = 3 feet x 3 feet Area of influence = 9 feet x 9 feet = 81 feet = 9 square yards | ||||
Cost per Square Yard | Depreciation Rate | Area of Influence | Degradation Cost | |
Asphalt Street | $45 | 60% | 9.0 | $243 |
Concrete Street | 0.0 | $0 | ||
Overlay | $10 | 50% | 9.0 | $45 |
Sealcoat | $1 | 80% | 9.0 | $7.20 |
Total Cost $295.20 | ||||
(B) Degradation costs will be reviewed and may be changed by resolution of the Board of Trustees.
(Prior Code, § 165.26.1) (Ord. 503, passed 7-7-2005; Ord. 577, passed 11-6-2014)
(A) The formula for determining that portion of the permit fee relating to administrative or management costs is as follows:
Labor (X) hours of staff time involved in connection with granting and oversight of permit =
Permit Fee for Administrative/Management Costs
(B) In connection with this formula, the following assumptions are made:
(1) Labor = hourly rate + benefits + indirect costs;
(2) Inspectors are paid $30 per hour;
(3) Engineers are paid $85 per hour;
(4) Clerical staff is paid $20 per hour;
(5) Benefits = 45% of salary; and
(6) Indirect costs = 25% of salary.
(C) Administrative/management costs will be reviewed and may be changed by resolution of the Board of Trustees.
(Prior Code, § 165.26.2) (Ord. 503, passed 7-7-2005; Ord. 577, passed 11-6-2014)
(A) Assumptions: street is 16 years old;
(B) Overlay is five years old;
(C) Sealcoat is one year old;
(D) Area of cut = three feet x three feet; and
(E) Area of influence = nine feet x nine feet = 81 square feet = nine square yards.
Cost per Square Yard | Depreciation Rate | Area of Influence | Degradation Cost | |
Concrete street | 0.0 | $0 | ||
Asphalt street | $45 | 60% | 9.0 | $243 |
Overlay | $10 | 50% | 9.0 | $45 |
Sealcoat | $1 | 80% | 9.0 | $7.20 |
Total cost | $295.20 |
(Prior Code, § 165.26.4.1) (Ord. 503, passed 7-7-2005; Ord. 577, passed 11-6-2014)