(A) Generally. Specific projects or activities may be exempt from all or part of the informational requirements listed below. Exemptions are detailed in §§ 56.020 and 56.070. If a project or activity is exempt from any or all requirements of this chapter, an application should be filed listing the exemption criteria met, in lieu of the information requirements listed below. This level of detailed information is not required from individual lots, disturbing less than 10,000 square feet of land, developed within a larger permitted project site. Review and approval of the lots is covered under § 56.088.
(B) Elements of permit submittal. The different elements of a permit submittal include a draft notice of intent (NOI), proof of publication of a public notice, construction plans, a stormwater drainage technical report, a stormwater pollution prevention plan for active construction sites, a post-construction stormwater pollution prevention plan, and any other necessary supporting information. All plans, reports, calculations, and narratives shall be signed and sealed by a professional engineer or a licensed surveyor, registered in the State of Indiana.
(C) Draft notice of intent.
(1) The NOI is a standard form developed by IDEM which requires general project information. As part of the city stormwater management permit application package, the NOI form should be completed in full based on data and information available at the time of application.
(2) An updated version of this form, accompanied by proof of publication in a newspaper of general circulation in the affected area that notified the public that a construction activity is to commence, will need to be resubmitted later after the stormwater management permit is granted and at least 48 hours prior to commencement of construction. The publication must include the following language:
(Company name, address) is submitting an NOI letter to notify the city and the State Department of Environmental Management of our intent to comply with the requirements of the city stormwater code, as well as the requirements of 327 I.A.C. 15-5 and 327 I.A.C. 15-13, to discharge stormwater from construction activities for the following project: (name of the construction project, address of the location of the construction project). Run-off from the project site will discharge to (stream(s) receiving the discharge(s)).
(D) Construction plans. Construction plan sheets and an accompanying narrative report shall describe and depict the existing and proposed conditions. Note that in order to gain an understanding of and to evaluate the relationship between the proposed improvements for a specific project section/phase and the proposed improvements for an overall multi-section (phased) project, the detailed information requested herein for the first section/phase being permitted must be accompanied by an overall project plan that includes the location, dimensions, and supporting analyses of all detention/retention facilities, primary conveyance facilities, and outlet conditions. Construction plans need to include items listed in the application checklist provided in the City of Lebanon Stormwater Technical Standards Manual.
(E) Stormwater drainage technical report. A written stormwater drainage technical report must contain a discussion of the steps taken in the design of the stormwater drainage system. Note that in order to gain an understanding of and to evaluate the relationship between the proposed improvements for a specified project section/phase and the proposed improvements for an overall multi-section (phased) project, the detailed information requested herein for the first section/phase being permitted must be accompanied by an overall project plan that includes the location, dimensions, and supporting analyses of all detention/retention facilities, primary conveyance facilities, and outlet conditions. The technical report needs to include items listed in the application checklist provided in the City of Lebanon Stormwater Technical Standards Manual.
(F) Stormwater pollution prevention plan for construction sites. For sites with total disturbance of one acre or more, a stormwater pollution prevention plan associated with construction activities must be designed to, at least, meet the requirements of this chapter. The SWPPP and construction plans must include the items listed in the application checklist provided in the City of Lebanon Stormwater Technical Standards Manual. For land disturbances totaling 10,000 square feet or more of land area but less than one acre, appropriate erosion and sediment control measures that are consistent with the City of Lebanon Technical Standards Manual must be designed and shown on the plans.
(G) Post-construction stormwater pollution prevention plan. For sites with total land disturbance of 10,000 square feet or more of total land area, a post-construction stormwater pollution prevention plan must be designed to, at least, meet the requirements of this chapter and must include the information provided in the City of Lebanon Stormwater Technical Standards Manual. The post- construction storm water pollution prevention plan must include items listed in the application checklist provided in the City of Lebanon Stormwater Technical Standards Manual.