§ 150.12 PERMIT FEES; DEPOSITS; BONDS.
   The permit fees and charges applicable to all development, building or construction within the village shall be those fees and charges as set forth herein.
One & Two Family Residential Structures
New structure
1.75% of construction costs*
Addition
1.75% of construction costs*
Interior remodel
1.75% of construction costs*
Garage
1.75% of construction costs*
Temporary/conditional occupancy
$100 and cash bond of $2,500
Permit extension
1.75% of remaining construction cost*
*Plus all applicable deposit, bond, tap and meter fee requirements
 
Miscellaneous Residential Permit Fees
Above ground swimming pool/hot tub
$200
In-ground swimming pool
1.5% construction cost + $150 plan review
Driveway
$125
Walkway or patio
$75
Fence
$100
Generator
$150 per unit
HVAC or boiler replacement
$75 per unit
HVAC system - new
1.5% of construction cost - min. $75
Lawn sprinkler/irrigation system
$75
Roof - new
$125
Roof repair
$75
Accessory structure, including but not limited to: deck, gazebo, pergola, shed; not listed separately
$175
Repairs, alterations, including but not limited to: windows, siding, drain tile, plumbing, electric; not listed separately
1.5% of construction cost - min. $75
 
All Structures (Excluding, One & Two Family Residential)
New structure/remodel/add ition under
   $1,000,00 in construction costs
   $1,000,000 - $5,000,000 in construction costs
   over $5,000,000 in construction costs
 
1.5% of construction cost + other fees**
1.0% of construction cost added to above
0.5% of construction cost added to above
Plumbing - new/repairs/alteration s
$100 up to 5 fixtures + $10 each additional fixture
Electric - new/repairs/alteration s
1.5% of construction cost - min. $100 + $10 per circuit
HVAC or boiler - new/repairs/replacem ent
1.5% of construction cost - min. $100 + $25 per unit
Parking lot - new/resurface
1.5% of construction cost - min. $75
Repairs, alterations, including but not limited to: windows, siding, drain tile, plumbing, electric; not listed separately
1.5% of construction cost - min. $75
Permit extension
1.5% of remaining construction cost**
Occupancy - final multi-family
$50 per dwelling unit
Occupancy - final other
$100
Occupancy - temporary/conditional
$100 and $5,000 cash bond
**Plus all applicable plumbing, electric, HVAC, tap, occupancy, deposit and bond fees and requirements.
 
 
Demolition
One & Two Family Structures
$500***
Multi-Family
1.5% of demolition cost - min. $500***
Non-Residential
1.5% of demolition cost - min. $500***
Residential garage/accessory structure
$50
***Plus $2,500 required Site Management Bond
 
 
Tap & Water Fees
Water tap
$750
Sewer tap
$750
Water use during construction
$300
Meter & connection fee
$500
 
 
Signs
Illuminated
$125 each
Non-illuminated
$75
Face change
$75
 
 
Contractor License
 
General
$75 annually
All other contractors
$50 annually
 
 
Elevators
 
New elevator
$250 + $125 for each failed inspection
Safety testing inspection
$125 each
Semi-annual inspection
$60 each
 
 
In-House Review Fees
 
In-house review fees (if applicable)
$100 initial hour + $50 each additional hour/resubmittal
 
   (A)   Reimbursement of Fees Agreement. Upon filing a permit application with the village, the applicant shall be required to execute a Reimbursement of Fees Agreement in a form approved by the Village Attorney, requiring the reimbursement of all out-of- pocket costs and any in-house review fees incurred by the village in relation to the application. The applicant shall also be required to provide a deposit, in accordance with the following schedule:
One & Two Family Structures
New construction
$2,500
Addition
$1,000
Interior remodel
$250
Garage
$500
All Other Structures
 
New construction/addition
$5,000
Alterations/remodel
$500
 
If the deposit is not sufficient to cover the out-of-pocket costs and in-house review fees incurred, the applicant will be required to pay any outstanding amounts prior to issuance of an occupancy permit. Upon final payment of all costs incurred by the village, the village shall refund the remaining balance of the deposit to the applicant.
   (B)   Right-of-way bonds.
      (1)   Bond requirement; timing of payment amount. Prior to the issuance of a building permit for each lot where street or sidewalk improvements are being installed, a cash bond shall be deposited with the village to indemnify the village against damage to the streets, curbs, and sidewalks and parkways, and to insure the proper installation, repair and/or complete restoration of streets, curbs, sidewalks and/or parkways in accordance with the instructions of the Director of Fire and Building. The village shall be under no obligation to pay interest on this money. It shall be the responsibility of the general contractor to notify the village of any streets, curbs sidewalks or parkways that were damaged prior to the start of construction on a lot. The cash bond shall be submitted in accordance with the following schedule:
 
Sidewalk/parkway opening
$500
V Street opening
$1,000
Full street opening
$1,500
 
      (2)   Bond refund. Upon the final completion of all the work under the permit, so much of such deposit as necessary to reimburse the village for the repair and/or restoration of the damaged streets, curbs, sidewalks or parkways shall be retained by the village and the remainder shall be returned to the depositor; provided, however, that nothing herein contained shall preclude the village from maintaining an action against any person or persons to recover for damage done to any street, sidewalk or parkway.
   (C)   Site management bond.
      (1)   Bond requirement; timing of payment amount. If a permit is to be issued for the demolition of a dwelling the applicant shall post with the village, at the time of issuance of such permit, a site management bond in the amount of $2,500 cash. Such bond shall be in addition to all other application and processing fees, costs, escrows, and bonds.
      (2)   Right to draw on bond. The village shall have the right at all times, at its option, to draw on the site management bond for the costs (including without limitation legal fees and administrative expenses), incurred or to be incurred by the village in exercising any of its rights in the event (a) the applicant undertakes any work in violation of any provision of the Building Codes and Regulations, or of any permit issued or plan approved, or (b) the applicant fails or refused to complete any work authorized by any permit issued under the Building Codes and Regulations in accordance with all plans approved in connection with said permit. The village's determination of such costs shall be based either on costs actually incurred by the village or on the village's reasonable estimates of costs to be incurred.
      (3)   Replenishment of bond. If the village draws on the site management bond, then the applicant shall replenish the bond to the full amount required by this chapter. Immediately after written demand therefore is made to the applicant by the village. Applicant's failure to replenish the bond shall result in cancellation of the related permit, which permit shall not be therefore reissued except after the filing of a new application, payment of the permit fee(s), and establishment of a new site management bond.
      (4)   Return of unused bond. The village shall return all unused portions of the site management bond to the applicant, without interest, as follows:
         (a)   If the permit authorizes only demolition work, and no construction work is scheduled to take place within 30 days after the completion of demolition, then the village shall return the bond within 30 days after the final inspection of the restoration of the subject property and approval of the work by the Director of Fire and Building.
         (b)   If the permit authorizes any construction work in addition to demolition work, then the village shall return the money within 30 days after issuance of a final certificate of occupancy for such new structure.
   (D)   Fee payment. In the absence of provisions to the contrary, all permit fees shall be paid in advance at the time of building permit application.
   (E)   Re-inspection fee. Permit fees shall include all required building, electrical, plumbing, and mechanical inspections required for project completion. For each failed inspection, a re-inspection fee of $75 will be assessed. Said fee must be paid prior to performance of the re-inspection.
   (F)   Posted notice of rules and regulations. The applicant shall post on the subject property in a prominent place a sign containing notice of the rules and regulations applicable to construction of a new principal structure in advance of the commencement of work. Such sign shall be maintained on the subject property until all work on the subject property has been completed and approved or until removal is approved by the Director of Fire and Building. The sign shall be supplied by the village and provided upon permit issuance. A fee of $50 will be assessed per sign.
   (G)   Work without permit. When work requiring a permit has been started prior to issuance of such permit, the permit fee shall be double the amount of the standard permit fee for such work. The accompanying fine shall not exceed $750. A stop work order may also be issued subject to the requirements of § 150.16.
(Ord. 1123, passed 1-28-20)