The following actions shall be violations of this article:
A. Where a permit is required, failure to obtain a permit prior to the start of grading activity;
B. Failure to call for inspections as required by this article;
C. Once grading activity has begun, failure to complete the grading activity and install the necessary erosion and sedimentation control, stormwater management, and slope stabilization measures, in a timely manner;
D. Failure to maintain temporary and permanent erosion and sedimentation control measures, the stormwater management system, or slope stabilization measures;
E. Conduct work on a site which exceeds the scope of work outlined in the approved plans;
F. Damage or otherwise impede the function of a stormwater system;
G. Export sediment from a site in a manner not authorized by this article;
H. Continue work at a site after a stop work order has been placed;
I. Discharge stormwater in a manner not authorized by this article;
J. Failure to correct a hazard as outlined in section 8.7.110 of this article; and