921.06 WATER TAP FEE.
   The charge to install a new water tap connecting to the water system of the Village shall be as provided by Council. The charge for installation of water tap shall be paid to the Village in advance accompanied by such deposit as provided by the Manager. In the event the deposit is insufficient to cover the actual costs, the person requesting the tap shall pay the balance due over and above the amount deposited.
   Water tap fees will be as follows:
Line Size
Tap Fee
Capacity Charge*
3/4"
$375.00
$7,400.00
1"
375.00
13,160.00
1 ½"
375.00
29,600.00
2"
375.00
52,630.00
3"
375.00
118,410.00
4"
375.00
210,500.00
6"
375.00
473,640.00
8"
375.00
842,030.00
   *Fifty percent of capacity charge is for Fire Protection only.
    (Ord. 22-2021. Passed 6-15-21.)
   (b)   Pre-purchase of Water and Sewer Tap or Capacity Fee. As of the effective date of Ordinance 01-2021, any type or capacity permit approved must be utilized within 180 days of permit approval. If the utilization of the approved permit is more than 180 days, the difference between the original tap or capacity fee and any increase in tap or capacity fee must be paid to the Village prior to any Village inspection and/or approval of the water meter.
   (c)   A water tap and capacity fee are required for each address.
(Ord. 29-2021. Passed 7-6-21.)