§ 150.35 REVISIONS TO THE 2018 EDITION INTERNATIONAL MECHANICAL CODE.
   (A)   The following revisions and amendments are based on the 2018 Edition of the International Mechanical Code and are intended for application to the most recent adopted edition. If conflicts of application or interpretation exist between this section and the most recently adopted code, the Code Official shall refer to the aforementioned editions for any revision or amendment in conflict.
   (B)   The following revisions or amendments supersede the actual text of the code as published as it pertains to that section only.
   (C)   The following specific sections have been revised in part or total to read as follows:
   101.1 Title (INSERT) The Village of Itasca, Illinois.
   106.3.1 Construction documents (DELETE) ‘...two or more sets..." (INSERT) Four (4) sets, all of which must be signed and sealed by an Illinois licensed and registered architect. structural engineer, or professional engineer.
      (INSERT at the end of the paragraph) One (1) of the drawing pages shall give details as vent schedule heat loss calculation units, exhaust fans and other equipment, sizes, etc.
   106.4.3.1 Expiration. (ADD) New Section. Every permit will be good for a period of one (1) year from date of approval. Extensions up to 180 days may be requested in writing and may be granted by the Building Official upon demonstration by the applicant of justifiable cause. A request of an extension shall include the following: (1) an explanation of the hardship which resulted in the work not being completed; and (2) a detailed description of all work which has not yet been completed and a timeline for completion. Extensions must also comply with Section 150.90 Building Permit Time Limits. Furthermore, for each subsequent extension beyond the initial one, the fee shall increase by 25% over the previous renewal fee (i.e., the second renewal fee would be 50% of the original permit fee and 75% for a third renewal).
      Permit renewal fees pursuant to Section 150.80 Schedule of Fees, must be paid prior to issuance of an extension.
   106.5 Fees (INSERT) see Village Code Section 150.80, Schedule of Fees.
   106.5.2 Fee schedule (INSERT) see Village Code Section 150.80, Schedule of Fees.
   106.5.3 Fee refunds. (DELETE) Entire Section.
   108.4 Penalties (INSERT) see Village Code Section 150.99, Penalty.
   108.5 Penalties (INSERT) see Village Code Section 150.99, Penalty.
   109.0 Means of Appeal (DELETE): entire section. (INSERT) See the amendments to the International Building Code Section 113 Board of Appeals.
   301.11 Plumbing connections. (DELETE) International Plumbing Code. (INSERT) State of Illinois Plumbing Code.
   1002.1 General (DELETE) International Plumbing Code. (INSERT) State of Illinois Plumbing Code.
   1005.2 Potable water supply. (DELETE) International Plumbing Code. (INSERT) State of Illinois Plumbing Code.
   1006.6.13 Safety and relief valve discharge. (DELETE) International Plumbing Code. (INSERT) State of Illinois Plumbing Code.
   1008.2 Discharge. (DELETE) International Plumbing Code. (INSERT) State of Illinois Plumbing Code.
   1009.3 Open-type expansion tanks. (DELETE) International Plumbing Code. (INSERT) State of Illinois Plumbing Code.
   1101.4 Water Connection. (DELETE) International Plumbing Code. (INSERT) State of Illinois Plumbing Code.
   1401.2 Potable water supply. (DELETE) International Plumbing Code. (INSERT) State of Illinois Plumbing Code.
   Delete References to the following:
   ICC EC      ICC Electric Code
   IEBC      International Existing Building Code
(Ord. 1464-08, passed 11-4-08; Am. Ord. 2010-22, passed 3-1-22)