7-5-1: PERMITS:
   A.   In addition to any necessary building permit, site development permits shall be required for any proposed construction or improvement or substantial alteration within flood-prone areas. Such permit shall not be issued until all other necessary permits have been received from those governmental agencies from which approval is required by Federal, State or local laws. Any proposed work must be subject to the provisions of Section 7-1-1000 of this Title. The permit application will be reviewed to assure that any proposed construction is:
      1.   Designed and anchored to prevent flotation, collapse or lateral movement of the structure;
      2.   Constructed with materials and utility equipment resistant to flood damage; and
      3.   Constructed by methods and practices that minimize flood damage.
   B.   At the time of issuing a building permit, the following information will be noted and recorded by the Village:
      1.   Elevation of the lowest floor (including basement).
      2.   Where the elevation of the lowest floor is below grade on one or more sides, the elevation of the floor immediately above.
      3.   Where a structure is to be floodproofed, the elevation to which such floodproofing extends. (Ord. 96-570, 8-13-1996)