§ 154.37 DUTIES AND RESPONSIBILITIES OF THE FLOODPLAIN ADMINISTRATOR.
   The floodplain administrator shall perform, but not be limited to, the following duties:
   (A)   Review all floodplain development applications and issue permits for all proposed development within special flood hazard areas to assure that the requirements of this chapter have been satisfied.
   (B)   Advise permittee that additional federal or state permits (wetlands, endangered species, erosion and sedimentation control, CAMA, riparian buffers, mining, etc.) may be required, and require that copies of such permits be provided and maintained on file with the floodplain development permit.
   (C)   Notify adjacent communities and the North Carolina Department of Crime Control and Public Safety, Division of Emergency Management, State Coordinator for the National Flood Insurance Program prior to any alteration or relocation of a watercourse, and submit evidence of such notification to the Federal Emergency Management Agency (FEMA).
   (D)   Assure that maintenance is provided within the altered or relocated portion of said watercourse so that the flood-carrying capacity is not diminished.
   (E)   Prevent encroachments into floodways and non-encroachment areas unless the certification and flood hazard reduction provisions of this chapter are met.
   (F)   Obtain actual elevation (in relation to mean sea level) of the reference level (including basement) and all attendant utilities of all new or substantially improved structures, in accordance with § 154.36(C).
   (G)   Obtain actual elevation (in relation to mean sea level) to which all new and substantially improved structures and utilities have been floodproofed, in accordance with § 154.36(C).
   (H)   Obtain actual elevation (in relation to mean sea level) of all public utilities in accordance with § 154.36(C).
   (I)   When floodproofing is utilized for a particular structure, obtain certifications from a registered professional engineer or architect in accordance with §§ 154.21 and 154.36(C).
   (J)   Where interpretation is needed as to the exact location of boundaries of the special flood hazard areas (for example, where there appears to be a conflict between a mapped boundary and actual field conditions), make the necessary interpretation. The person contesting the location of the boundary shall be given a reasonable opportunity to appeal the interpretation as provided in this subchapter.
   (K)   When base flood elevation (BFE) data has not been provided in accordance with § 154.05, obtain, review, and reasonably utilize any base flood elevation (BFE) data, along with floodway data or non-encroachment area data available from a federal, state, or other source, including data developed pursuant to this chapter, in order to administer the provisions of this chapter.
   (L)   When base flood elevation (BFE) data is provided but no floodway nor non-encroachment area data has been provided in accordance with § 154.05, obtain, review, and reasonably utilize any floodway data or non-encroachment area data available from a federal, state, or other source in order to administer the provisions of this chapter.
   (M)   When the lowest ground elevation of a parcel or structure in a special flood hazard area is above the base flood elevation, advise the property owner of the option to apply for a Letter of Map Amendment (LOMA) from FEMA. Maintain a copy of the Letter of Map Amendment (LOMA) issued by FEMA in the floodplain development permit file.
   (N)   Permanently maintain all records that pertain to the administration of this chapter and make these records available for public inspection.
   (O)   Make on-site inspections of work in progress. As the work pursuant to a floodplain development permit progresses, the floodplain administrator shall make as many inspections of the work as may be necessary to ensure that the work is being done according to the provisions of the local ordinance and the terms of the permit. In exercising this power, the floodplain administrator has a right, upon presentation of proper credentials, to enter on any premises within the jurisdiction of the community at any reasonable hour for the purposes of inspection or other enforcement action.
   (P)   Issue stop-work orders as required. Whenever a building or part thereof is being constructed, reconstructed, altered, or repaired in violation of this chapter, the floodplain administrator may order the work to be immediately stopped. The stop-work order shall be in writing and directed to the person doing the work. The stop-work order shall state the specific work to be stopped, the specific reason(s) for the stoppage, and the condition(s) under which the work may be resumed. Violation of a stop-work order constitutes a misdemeanor.
   (Q)   Revoke floodplain development permits as required. The floodplain administrator may revoke and require the return of the floodplain development permit by notifying the permit holder in writing stating the reason(s) for the revocation. Permits shall be revoked for any substantial departure from the approved application, plans, or specifications; for refusal or failure to comply with the requirements of state or local laws; or for false statements or misrepresentations made in securing the permit. Any floodplain development permit mistakenly issued in violation of an applicable state or local law may also be revoked.
   (R)   Make periodic inspections throughout all special flood hazard areas within the jurisdiction of the community. The floodplain administrator and each member of his or her inspections department shall have a right, upon presentation of proper credentials, to enter on any premises within the territorial jurisdiction of the department at any reasonable hour for the purposes of inspection or other enforcement action.
   (S)   Follow through with corrective procedures of this chapter.
   (T)   Review, provide input, and make recommendations for variance requests.
   (U)   Maintain a current map repository to include, but not limited to, the FIS Report, FIRM and other official flood maps and studies adopted in accordance with § 154.05, including any revisions thereto including Letters of Map Change, issued by FEMA. Notify state and FEMA of mapping needs.
   (V)   Coordinate revisions to FIS reports and FIRMs, including Letters of Map Revision Based on Fill (LOMR-F) and Letters of Map Revision (LOMR).
('85 Code, § 8-4.4c.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18)
§ 154.38 VARIANCE PROCEDURES.
   (A)   The Board of Adjustment as established by the town, hereinafter referred to as the “appeal board,” shall hear and decide requests for variances from the requirements of this chapter.
   (B)   Any person aggrieved by the decision of the appeal board may appeal such decision to the Court, as provided in G.S. Chapter 7A.
   (C)   Variances may be issued for:
      (1)   The repair or rehabilitation of historic structures upon the determination that the proposed repair or rehabilitation will not preclude the structure's continued designation as a historic structure and that the variance is the minimum necessary to preserve the historic character and design of the structure.
      (2)   Functionally dependent facilities if determined to meet the definition as stated in § 154.03, provided provisions of this chapter have been satisfied, and such facilities are protected by methods that minimize flood damages.
      (3)   Any other type of development provided it meets the requirements stated in this section.
   (D)   In passing upon variances, the appeal board shall consider all technical evaluations, all relevant factors, all standards specified in other sections of this chapter, and:
      (1)   The danger that materials may be swept onto other lands to the injury of others;
      (2)   The danger to life and property due to flooding or erosion damage;
      (3)   The susceptibility of the proposed facility and its contents to flood damage and the effect of such damage on the individual owner;
      (4)   The importance of the services provided by the proposed facility to the community;
      (5)   The necessity to the facility of a waterfront location as defined under § 154.03 as a functionally dependent facility, where applicable;
      (6)   The availability of alternative locations, not subject to flooding or erosion damage, for the proposed use;
      (7)   The compatibility of the proposed use with existing and anticipated development;
      (8)   The relationship of the proposed use to the comprehensive plan and floodplain management program for that area;
      (9)   The safety of access to the property in times of flood for ordinary and emergency vehicles;
      (10)   The expected heights, velocity, duration, rate of rise, and sediment transport of the floodwaters and the effects of wave action, if applicable, expected at the site; and
      (11)   The costs of providing governmental services during and after flood conditions including maintenance and repair of public utilities and facilities such as sewer, gas, electrical and water systems, and streets and bridges.
   (E)   A written report addressing each of the above factors shall be submitted with the application for a variance.
   (F)   Upon consideration of the factors listed above and the purposes of this chapter, the appeal board may attach such conditions to the granting of variances as it deems necessary to further the purposes of this chapter.
   (G)   Any applicant to whom a variance is granted shall be given written notice specifying the difference between the base flood elevation (BFE) and the elevation to which the structure is to be built and that such construction below the base flood elevation increases risks to life and property, and that the issuance of a variance to construct a structure below the base flood elevation will result in increased premium rates for flood insurance up to $25 per $100 of insurance coverage. Such notification shall be maintained with a record of all variance actions, including justification for their issuance.
   (H)   The floodplain administrator shall maintain the records of all appeal actions and report any variances to the Federal Emergency Management Agency and the State of North Carolina upon request.
   (I)   Conditions for variances:
      (1)   Variances shall not be issued when the variance will make the structure in violation of other federal, state, or local laws, regulations, or ordinances.
      (2)   Variances shall not be issued within any designated floodway or non-encroachment area if the variance would result in any increase in flood levels during the base flood discharge.
      (3)   Variances shall only be issued upon a determination that the variance is the minimum necessary, considering the flood hazard, to afford relief.
      (4)   Variances shall only be issued prior to development permit approval.
      (5)   Variances shall only be issued upon:
         (a)   A showing of good and sufficient cause;
         (b)   A determination that failure to grant the variance would result in exceptional hardship; and
         (c)   A determination that the granting of a variance will not result in increased flood heights, additional threats to public safety, or extraordinary public expense, create nuisance, cause fraud on or victimization of the public, or conflict with existing local laws or ordinances.
      (6)   A variance may be issued for solid waste disposal facilities or sites, hazardous waste management facilities, salvage yards, and chemical storage facilities that are located in special flood hazard areas provided that all of the following conditions are met:
         (a)   The use serves a critical need in the community;
         (b)   No feasible location exists for the use outside the special flood hazard area; and
         (c)   The reference level of any structure is elevated or floodproofed to at least the regulatory flood protection elevation.
      (7)   The use complies with all other applicable federal, state and local laws.
      (8)   The town has notified the Secretary of the North Carolina Department of Public Safety of its intention to grant a variance at least 30 calendar days prior to granting the variance.
(‘85 Code, § 8-4.4e.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 02-12, passed 10-14-02; Am. Ord. 03-01, passed 2-24-03; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18; Am. Ord. 21-10, passed 6-15-21)
§ 154.39 INSPECTIONS OF THE WORK IN PROGRESS.
   As the work pursuant to a permit progresses, the local Building Inspector and Development Services Officer shall make as many inspections of the work as may be necessary to ensure that the work is being done according to the provisions of this chapter and the terms of the permit. In exercising this power, the Building Inspector and Development Services Officer has a right, upon presentation of proper credentials, to enter on any premises within the territorial jurisdiction at any reasonable hour for the purposes of inspection or other enforcement action.
(‘85 Code, § 8-4.4d.1.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18; Am. Ord. 20-11, passed 9-3-20)
§ 154.40 STOP ORDERS.
   Whenever a building or part thereof is being constructed, reconstructed, altered, or repaired in violation of this chapter, the Building Inspector or Development Services Officer may order the work to be immediately stopped. The stop order shall be in writing and directed to the person doing the work. The stop order shall state the specific work to be stopped, the specific reasons for the stoppage and the conditions under which the work may be resumed. Violation of a stop order constitutes a misdemeanor.
(‘85 Code, § 8-4.4d.2.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 06-06, passed 5- 22-06; Am. Ord. 18-13, passed 8-6-18; Am. Ord. 20-11, passed 9-3-20) Penalty, see § 154.99
§ 154.41 REVOCATION OF PERMITS.
   The local Building Inspector and Development Services Officer may revoke and require the return of the development permit by notifying the permit-holder in writing stating the reason for revocation. Permits shall be revoked for any substantial departure from the approved application, plans or specifications; for refusal or failure to comply with the requirements of state or local laws; or for false statements or misrepresentations made in securing the permit. Any permit mistakenly issued in violation of an applicable state or local law may also be revoked.
(‘85 Code, § 8-4.4d.3.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18; Am. Ord. 20-11, passed 9-3-20)
§ 154.42 PERIODIC INSPECTIONS.
   The local Building Inspector and each member of his or her Inspections Department shall have a right, upon presentation of proper credentials, to enter on any premises within the territorial jurisdiction of the department at any reasonable hour for the purposes of inspection or other enforcement action.
('85 Code, § 8-4.4d.4.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18)
§ 154.43 VIOLATIONS TO BE CORRECTED.
   When the local Building Inspector or Development Services Officer finds violations of applicable state and local laws, it shall be his or her duty to notify the owner of the building of the violation. The owner shall immediately remedy the violations of law.
(‘85 Code, § 8-4.4d.5.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18; Am. Ord. 20-11, passed 9-3-20) Penalty, see § 154.99