(A) Residential construction. New construction and substantial improvement of any residential structure (including manufactured homes) shall have the reference level, including basement, elevated no lower than the regulatory flood protection elevation, as defined in § 154.03.
(B) Non-residential construction. New construction and substantial improvement of any commercial, industrial, or other non-residential structure shall have the reference level, including basement, elevated no lower than the regulatory flood protection elevation, as defined in § 154.03. Structures located in A, AE and A1-30 Zones may be floodproofed to the regulatory flood protection elevation in lieu of elevation provided that all areas of the structure, together with attendant utility and sanitary facilities, below the regulatory flood protection elevation are watertight with walls substantially impermeable to the passage of water, using structural components having the capability of resisting hydrostatic and hydrodynamic loads and the effect of buoyancy. For AO Zones, the floodproofing elevation shall be in accordance with this chapter. A registered professional engineer or architect shall certify that the standards of this division are satisfied. Such certification shall be provided to the Floodplain Administrator as set forth in § 154.36(C), along with the operational and maintenance plans.
(C) Manufactured homes.
(1) New or replacement manufactured homes shall be elevated so that the reference level of the manufactured home is no lower than the regulatory flood protection elevation, as defined in § 154.03.
(2) Manufactured homes shall be securely anchored to an adequately anchored foundation to resist flotation, collapse, and lateral movement, either by engineer certification, or in accordance with the most current edition of the State of North Carolina Regulations for Manufactured Homes, adopted by the Commissioner of Insurance pursuant to G.S. § 143-143.15 or a certified engineered foundation. Additionally, when the elevation would be met by an elevation of the chassis 36 inches or less above the grade at the site, the chassis shall be supported by reinforced piers or engineered foundation. When the elevation of the chassis is above 36 inches in height, an engineering certification is required.
(3) All enclosures or skirting below the lowest floor shall meet the requirements of division (D) of this section.
(4) An evacuation plan must be developed for evacuation of all residents of all new, substantially improved or substantially damaged manufactured home parks or subdivisions located within flood prone areas. This plan shall be filed with and approved by the floodplain administrator and the local emergency management coordinator.
(D) Elevated buildings. Fully enclosed areas of new construction and substantially improved structures, which are below the lowest floor:
(1) Shall not be designed or used for human habitation, but shall only be used for parking of vehicles, building access, or limited storage of maintenance equipment used in connection with the premises. Access to the enclosed area shall be the minimum necessary to allow for parking of vehicles (garage door) or limited storage of maintenance equipment (standard exterior door), or entry to the living area (stairway or elevator). The interior portion of such enclosed area shall not be finished or partitioned into separate rooms, except to enclose storage areas;
Exception: Elevators and accessible interior stairs may be finished if approved flood proof materials are used below the RFPE.
Exception: elevators and accessible interior stairs may be finished if approved floodproof materials are used below the RFPE.
(2) Shall be constructed entirely of flood resistant materials, up to the regulatory flood protection elevation;
(3) Shall include, in Zone AE, flood openings to automatically equalize hydrostatic flood forces on walls by allowing for the entry and exit of floodwaters. To meet this requirement, the openings must either be certified by a professional engineer or architect or meet or exceed the following minimum design criteria:
(a) A minimum of two flood openings on different sides of each enclosed area subject to flooding;
(b) The total net area of all flood openings must be at least one square inch for each square foot of enclosed area subject to flooding;
(c) If a building has more than one enclosed area, each enclosed area must have flood openings to allow floodwaters to automatically enter and exit;
(d) The bottom of all required flood openings shall be no higher than one foot above the adjacent grade;
(e) Flood openings may be equipped with screens, louvers, or other coverings or devices, provided they permit the automatic flow of floodwaters in both directions; and
(f) Enclosures made of flexible skirting are not considered enclosures for regulatory purposes, and, therefore, do not require flood openings. Masonry or wood underpinning, regardless of structural status, is considered an enclosure and requires flood openings as outlined above;
(4) Shall allow, in Coastal High Hazard Areas (Zone VE), breakaway walls, open wood latticework or insect screening, provided it is not part of the structural support of the building and is designed so as to breakaway, under abnormally high tides or wave action, without causing damage to the structural integrity of the building, provided the following design specifications are met:
(a) Material shall consist of open wood latticework or insect screening; or
(b) Breakaway walls shall meet the following design specifications:
1. Design safe loading resistance of each wall shall be not less than ten nor more than 20 pounds per square foot; or
2. Breakaway walls that exceed a design safe loading resistance of 20 pounds per square foot (either by design or when so required by state or local codes) shall be certified by a registered professional engineer or architect that the breakaway wall will collapse from a water load less than that which would occur during the base flood event, and the elevated portion of the building and supporting foundation system shall not be subject to collapse, displacement, or other structural damage due to the effects of wind and water loads acting simultaneously on all building components (structural and non-structural). The water loading values used shall be those associated with the base flood. The wind loading values used shall be those required by the North Carolina State Building Code.
(E) Additions/improvements.
(1) Additions and/or improvements to pre-FIRM structures when the addition and/or improvements in combination with any interior modifications to the existing structure are:
(a) Not a substantial improvement, the addition and/or improvements must be designed to minimize flood damages and must not be any more non-conforming than the existing structure.
(b) A substantial improvement, both the existing structure and the addition and/or improvements must comply with the standards for new construction.
(2) Additions and/or improvements to post-FIRM structures when the addition and/or improvements in combination with any interior modifications to the existing structure are:
(a) Not a substantial improvement, the addition and/or improvements only must comply with the standards for new construction; and
(b) A substantial improvement, both the existing structure and the addition and/or improvements must comply with the standards for new construction.
(4) Where an independent perimeter load-bearing wall is provided between the addition and the existing building, the addition(s) shall be considered a separate building and only the addition must comply with the standards for new construction.
(5) Any combination of repair, reconstruction, rehabilitation, addition or improvement of a building or structure taking place during a two year period, the cumulative cost of which equals or exceeds 50% of the market value of the structure before the improvement or repair is started must comply with the standards for new construction. For each building or structure, the two year period begins on the date of the first improvement or repair of that building or structure subsequent to the effective date of this chapter. Substantial damage also means flood-related damage sustained by a structure on two separate occasions during a ten- year period for which the cost of repairs at the time of each such flood event, on the average, equals or exceeds 25% of the market value of the structure before the damage occurred. If the structure has sustained substantial damage, any repairs are considered substantial improvement regardless of the actual repair work performed. The requirement does not, however, include either:
(a) Any project for improvement of a building required to correct existing health, sanitary or safety code violations identified by the building official and that are the minimum necessary to assume safe living conditions; or
(b) Any alteration of a historic structure provided that the alteration will not preclude the structure’s continued designation as a historic structure.
(F) Recreational vehicles. Recreational vehicles shall either:
(1) Temporary placement. Be on site for fewer than 180 consecutive days and be fully licensed and ready for highway use (a recreational vehicle is ready for highway use if it is on its wheels or jacking system, is attached to the site only by quick disconnect type utilities, and has no permanently attached additions); or
(2) Permanent placement. Recreational vehicles that do not meet the limitations of temporary placement shall meet all the requirements for new construction.
(G) Temporary non-residential structures. Prior to the issuance of a floodplain development permit for a temporary structure, the applicant must submit to the floodplain administrator a plan for the removal of such structure(s) in the event of a hurricane, flash flood or other type of flood warning notification. The following information shall be submitted in writing to the floodplain administrator for review and written approval:
(1) A specified time period for which the temporary use will be permitted. Time specified should not exceed three months, renewable up to one year;
(2) The name, address, and phone number of the individual responsible for the removal of the temporary structure;
(3) The time frame prior to the event at which a structure will be removed (i.e., minimum of 72 hours before landfall of a hurricane or immediately upon flood warning notification);
(4) A copy of the contract or other suitable instrument with the entity responsible for physical removal of the structure; and
(5) Designation, accompanied by documentation, of a location outside the special flood hazard area, to which the temporary structure will be moved.
(H) Accessory structures.
(1) When accessory structures (sheds, detached garages, etc.) are to be placed within a special flood hazard area, the following criteria shall be met:
(a) Accessory structures shall not be used for human habitation (including working, sleeping, living, cooking or restroom areas);
(b) Accessory structures shall not be temperature-controlled;
(c) Accessory structures shall be designed to have low flood damage potential;
(d) Accessory structures shall be constructed and placed on the building site so as to offer the minimum resistance to the flow of floodwaters;
(e) Accessory structures shall be firmly anchored in accordance with § 154.20;
(f) All service facilities such as electrical shall be installed in accordance with § 154.20; and
(g) Flood openings to facilitate automatic equalization of hydrostatic flood forces shall be provided below regulatory flood protection elevation in conformance with division (D) of this section.
(2) An accessory structure with a footprint less than 150 square feet that satisfies the criteria outlined above does not require an elevation or floodproofing certificate. Elevation or floodproofing certifications are required for all other accessory structures in accordance with § 154.36(C).
(3) Tanks. When gas and liquid storage tanks are to be placed within a special flood hazard area, the following criteria shall be met:
(a) Underground tanks. Underground tanks in flood hazard areas shall be anchored to prevent flotation, collapse or lateral movement resulting from hydrodynamic and hydrostatic loads during conditions of the design flood, including the effects of buoyancy assuming the tank is empty;
(b) Above-ground tanks, elevated. Above ground tanks in flood hazard areas shall be elevated to or above the regular flood protection elevation on a supporting structure that is designed to prevent flotation, collapse or lateral movement during conditions of the design flood. Tank-supporting structures shall meet the foundation requirements of the applicable flood hazard area;
(c) Above ground tanks, not elevated. Above-ground tanks that do not meet the elevation requirements of § 154.23 shall be permitted in flood hazard areas provided the tanks are designed, constructed, installed, and anchored to resist all flood- related and other loads, including the effects of buoyancy, during conditions of the design flood and without release of contents in the floodwaters or infiltration by floodwaters into the tanks. Tanks shall be designed, constructed, installed, and anchored to resist the potential buoyant and other flood forces acting on an empty tank during design flood conditions.
(d) Tank inlets and vents. Tank inlets, fill openings, outlets and vents shall be:
1. At or above the regulatory flood protection elevation or fitted with covers designed to prevent the inflow of floodwater or outflow of the contents of the tanks during conditions of the design flood; and
2. Anchored to prevent lateral movement resulting from hydrodynamic and hydrostatic loads, including the effects of buoyancy, during conditions of the design flood.
(4) Other development.
(a) Fences in regulated floodways and NEAs that have the potential to block the passage of floodwaters, such as stockade fences and wire mesh fences, shall meet the limitations of § 154.23.
(b) Retaining walls, sidewalks and driveways in regulated floodways and NEAs. Retaining walls and sidewalks and driveways that involve the placement of fill in regulated floodways shall meet the limitations of § 154.23.
(c) Roads and watercourse crossings in regulated floodways and NEAs. Roads and watercourse crossings, including roads, bridges, culverts, low-water crossings and similar means for vehicles or pedestrians to travel from one side of a watercourse to the other side, that encroach into regulated floodways shall meet the limitations of § 154.23.
(I) Tanks. When gas and liquid storage tanks are to be placed within a special flood hazard area, the following criteria shall be met:
(1) Underground tanks. Underground tanks in flood hazard areas shall be anchored to prevent flotation, collapse or lateral movement resulting from hydrodynamic and hydrostatic loads during conditions of the design flood, including the effects of buoyancy assuming the tank is empty;
(2) Above-ground tanks, elevated. Above ground tanks in flood hazard areas shall be elevated to or above the regular flood protection elevation on a supporting structure that is designed to prevent flotation, collapse or lateral movement during conditions of the design flood. Tank-supporting structures shall meet the foundation requirements of the applicable flood hazard area;
(3) Above-ground tanks, not elevated. Above-ground tanks that do not meet the elevation requirements of § 154.23 shall be permitted in flood hazard areas provided the tanks are designed, constructed, installed, and anchored to resist all flood- related and other loads, including the effects of buoyancy, during conditions of the design flood and without release of contents in the floodwaters or infiltration by floodwaters into the tanks. Tanks shall be designed, constructed, installed, and anchored to resist the potential buoyant and other flood forces acting on an empty tank during design flood conditions.
(4) Tank inlets and vents. Tank inlets, fill openings, outlets and vents shall be:
(a) At or above the regulatory flood protection elevation or fitted with covers designed to prevent the inflow of floodwater or outflow of the contents of the tanks during conditions of the design flood; and
(b) Anchored to prevent lateral movement resulting from hydrodynamic and hydrostatic loads, including the effects of buoyancy, during conditions of the design flood.
(J) Other development.
(1) Fences in regulated floodways and NEAs that have the potential to block the passage of floodwaters, such as stockade fences and wire mesh fences, shall meet the limitations of § 154.23.
(2) Retaining walls, sidewalks and driveways in regulated floodways and NEAs. Retaining walls and sidewalks and driveways that involve the placement of fill in regulated floodways shall meet the limitations of § 154.23.
(3) Roads and watercourse crossings in regulated floodways and NEAs. Roads and watercourse crossings, including roads, bridges, culverts, low-water crossings and similar means for vehicles or pedestrians to travel from one side of a watercourse to the other side, that encroach into regulated floodways shall meet the limitations of § 154.23.
(‘85 Code, § 8-4.5b.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 03-01, passed 2-24-03; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18; Am. Ord. 20-11, passed 9-3-20; Am. Ord. 21-10, passed 6-15-21; Am. Ord. 24-08, passed 6-18-24) Penalty, see §154.99
(A) All subdivision proposals shall be consistent with the need to minimize flood damage.
(B) All subdivision proposals shall have public utilities and facilities such as sewer, gas, electrical, and water systems located and constructed to minimize flood damage.
(C) All subdivisions proposals shall have adequate drainage provided to reduce exposure to flood hazards.
(D) Base flood elevation data should be provided for subdivision proposals and other proposed development which is greater than the lesser of 50 lots of five acres.
('85 Code, § 8-4.5c.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18) Penalty, see § 154.99
Coastal high hazard areas are special flood hazard areas established in § 154.05, and designated as Zones VE. These areas have special flood hazards associated with high velocity waters from storm surges or seismic activity and, therefore, in addition to meeting all requirements of this chapter with the exception of floodway and non-encroachment area provisions, the following provisions shall apply:
(A) All development shall:
(1) Be located landward of the reach of mean high tide;
(2) Be located landward of the first line of stable natural vegetation; and
(3) Comply with all applicable CAMA setback requirements.
(B) All new construction and substantial improvements shall be elevated so that the bottom of the lowest horizontal structural member of the lowest floor (excluding pilings or columns) is no lower than the regulatory flood protection elevation. Floodproofing shall not be utilized on any structures in coastal high hazard areas to satisfy the regulatory flood protection elevation requirements.
(C) All new construction and substantial improvements shall have the space below the lowest floor free of obstruction so as not to impede the flow of flood waters, with the following exceptions:
(1) Open wood latticework or insect screening may be permitted below the regulatory flood protection elevation for aesthetic purposes only and must be designed to wash away in the event of abnormal wave action and in accordance with § 154.21(D). Design plans shall be submitted in accordance with § 154.36(A)(4); or
(D) All new construction and substantial improvements shall be securely anchored to pile or column foundations. All pilings and columns and the structures attached thereto shall be anchored to resist flotation, collapse, and lateral movement due to the effect of wind and water loads acting simultaneously on all building components.
(1) Water loading values used shall be those associated with the base flood.
(2) Wind loading values used shall be those required by the current edition of the North Carolina State Building Code.
(E) For concrete pads, including patios, decks, parking pads, walkways, driveways, pool decks, etc. the following is required:
(1) Shall be structurally independent of the primary structural foundation system of the structure and not adversely affect structures through redirection of floodwaters or debris; and
(2) Shall be constructed to breakaway cleanly during design flood conditions, shall be frangible, and shall not produce debris capable of causing damage to any structure (the installation of concrete in small segments, (approximately four feet by four feet), that will easily break up during the base flood event, or score concrete in four by four feet maximum segments acceptable to meet the standard): and
(a) Reinforcing, including welded wire fabric, shall not be used in order to minimize the potential for concrete pads being a source of debris; and
(b) Pad thickness shall not exceed four inches; or
(c) Provide a design professional’s certification stating the design and method of construction to be used to meet the applicable criteria of this section.
(F) For swimming pools and spas, the following is required:
(1) Be designed to withstand all flood-related loads and load combinations.
(2) Be elevated so that the lowest horizontal structural member is elevated above the RFPE;
(3) Be designed and constructed to break away during design flood conditions without producing debris capable of causing damage to any structure; or
(4) Be sited to remain in the ground during design flood conditions without obstructing flow that results in damage to any structure.
(5) Registered design professionals must certify to local officials that a pool or spa beneath or near a VE Zone building will not be subject to flotation or displacement that will damage building foundations or elevated portions of the building or any nearby buildings during a coastal flood.
(6) Pool equipment shall be located above the RFPE whenever practicable. Pool equipment shall not be located beneath an elevated structure.
(G) All elevators, vertical platform lifts, chair lifts, etc., the following is required:
(1) Elevator enclosures must be designed to resist hydrodynamic and hydrostatic forces as well as erosion, scour, and waves.
(2) Utility equipment in coastal high hazard areas (VE Zones) must not be mounted on, pass through, or be located along breakaway walls.
(3) The cab, machine/equipment room, hydraulic pump, hydraulic reservoir, counter weight and roller guides, hoist cable, limit switches, electric hoist motor, electrical junction box, circuit panel, and electrical control panel are all required to be above RFPE. When this equipment cannot be located above the RFPE, it must be constructed using flood damage-resistant components.
(4) Elevator shafts/enclosures that extend below the RFPE shall be constructed with breakaway walls and flood vents installed.
(5) Flood damage- resistant materials can also be used inside and outside the elevator cab to reduce flood damage. Use only stainless steel doors and door frames below the BFE. Grouting of door frames and sills is recommended.
(6) If an elevator is designed to provide access to areas below the BFE, it shall be equipped with a float switch system that will activate during a flood and send the elevator cab to a floor above the RFPE.
(H) A registered professional engineer or architect shall certify that the design, specifications and plans for construction are in compliance with the provisions contained in divisions (C), (D) and (F) of this section and § 154.36 on the current version of the North Carolina “National Flood Insurance Program V-Zone Certification” form.
(I) Fill shall not be used for structural support. Limited non-compacted and non-stabilized fill may be used around the perimeter of a building for landscaping/aesthetic purposes provided it is demonstrated through coastal engineering analysis that the proposed fill would not result in any increase in the base flood elevation and not cause any adverse impacts by wave ramping and deflection to the subject structure or adjacent properties.
(J) There shall be no alteration of sand dunes which would increase potential flood damage.
(K) No manufactured homes shall be permitted except in an existing manufactured home park or subdivision. A replacement manufactured home may be placed on a lot in an existing manufactured home park or subdivision provided the anchoring and elevation standards of this section have been satisfied.
(Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18; Am. Ord. 20-11, passed 9-3-20; Am. Ord. 21-10, passed 6-15-21)
ADMINISTRATION
The Building Inspector and Development Services Officer, hereinafter referred to as the “Floodplain Administrator”, is hereby appointed to administer and implement the provisions of this chapter. In instances where the Floodplain Administrator receives assistance from others to complete tasks to administer and implement this chapter, the Floodplain Administrator shall be responsible for the coordination and community’s overall compliance with the National Flood Insurance Program and the provisions of this chapter.
(‘85 Code, § 8-4.4a.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18; Am. Ord. 20-11, passed 9-3-20)
(A) Application requirements. Application for a floodplain development permit shall be made to the floodplain administrator prior to any development activities located within special flood hazard areas. The following items shall be presented to the floodplain administrator to apply for a floodplain development permit:
(1) A plot plan drawn to scale which shall include, but shall not be limited to, the following specific details of the proposed floodplain development:
(a) The nature, location, dimensions, and elevations of the area of development/disturbance, existing and proposed structures, utility systems, grading/pavement areas, fill materials, storage areas, drainage facilities, and other development;
(b) The boundary of the special flood hazard area as delineated on the FIRM or other flood map as determined in § 154.05, or a statement that the entire lot is within the special flood hazard area;
(c) Flood zone(s) designation of the proposed development area as determined on the FIRM or other flood map as determined in § 154.05;
(d) The boundary of the floodway(s) or non-encroachment area(s) as determined in § 154.05;
(f) The old and new location of any watercourse that will be altered or relocated as a result of proposed development;
(g) The boundary and designation date of the coastal barrier resource system (CBRS) area or otherwise protected areas (OPA), if applicable; and
(h) Certification of the plot plan by a registered land surveyor.
(2) Proposed elevation, and method thereof, of all development within a special flood hazard area including but not limited to:
(a) Elevation in relation to NAVD 1988 of the proposed reference level (including basement) of all structures;
(b) Elevation in relation to NAVD 1988 to which any non-residential structure in Zone AE will be flood-proofed; and
(c) Elevation in relation to NAVD 1988 to which any proposed utility systems will be elevated or floodproofed;
(3) If floodproofing, a Floodproofing Certificate (FEMA Form 086-0-34) with supporting data and an operational plan that includes, but is not limited to, installation, exercise, and maintenance of floodproofing measures.
(4) A foundation plan, drawn to scale, which shall include details of the proposed foundation system to ensure all provisions of this chapter are met. These details include but are not limited to:
(a) The proposed method of elevation, if applicable (i.e., fill, solid foundation perimeter wall, solid backfilled foundation, open foundation on columns/posts/piers/piles/shear walls);
(b) Openings to facilitate equalization of hydrostatic flood forces on walls in accordance with § 154.21(D), when solid foundation perimeter walls are used in Zone AE;
1. V-Zone Certification with accompanying plans and specifications verifying the engineered structure and any breakaway wall designs; in addition, prior to the Certificate of Compliance/Occupancy issuance, a registered professional engineer or architect shall certify the finished construction is compliant with the design, specifications and plans for VE Zone construction. (Optional);
2. Plans for open wood latticework or insect screening, if applicable; and
3. Plans for non-structural fill, if applicable. If non-structural fill is proposed, it must be demonstrated through coastal engineering analysis that the proposed fill would not result in any increase in the base flood elevation or otherwise cause adverse impacts by wave ramping and deflection on to the subject structure or adjacent properties.
(5) Usage details of any enclosed areas below the regulatory flood protection elevation.
(6) Plans and/or details for the protection of public utilities and facilities such as sewer, gas, electrical, and water systems to be located and constructed to minimize flood damage.
(7) Copies of all other local, state and federal permits required prior to floodplain development permit issuance (wetlands, endangered species, erosion and sedimentation control, CAMA, riparian buffers, mining, etc.)
(8) Documentation for placement of recreational vehicles and/or temporary structures, when applicable, to ensure § 154.21(F) and (G) are met.
(9) A description of proposed watercourse alteration or relocation, when applicable, including an engineering report on the effects of the proposed project on the flood-carrying capacity of the watercourse and the effects to properties located both upstream and downstream; and a map (if not shown on plot plan) showing the location of the proposed watercourse alteration or relocation.
(B) Permit requirements. The floodplain development permit shall include, but not be limited to:
(1) A complete description of all the development to be permitted under the floodplain development permit (e.g. house, garage, pool, septic, bulkhead, cabana, pier, bridge, mining, dredging, filling, grading, paving, excavation or drilling operations, or storage of equipment or materials, etc.).
(2) The special flood hazard area determination for the proposed development per available data specified in § 154.05.
(3) The regulatory flood protection elevation required for the reference level and all attendant utilities.
(4) The regulatory flood protection elevation required for the protection of all public utilities.
(5) All certification submittal requirements with timelines.
(6) A statement that no fill material or other development shall encroach into the floodway or non-encroachment area of any watercourse unless the requirements of § 154.23 have been met.
(7) The flood openings requirements, if in Zones AE.
(8) Limitations of use of the enclosures below the lowest floor are parking, building access and limited storage only.
(9) A statement, if in Zone VE, that there shall be no alteration of sand dunes which would increase potential flood damage.
(10) A statement, if in Zone VE, that there shall be no fill used for structural support.
(11) A statement that all materials below BFE/RFPE must be flood resistant materials.
(C) Certification requirements.
(1) Elevation certificates.
(a) An elevation certificate (FEMA Form 086-0-33) is required prior to the actual start of any new construction. It shall be the duty of the permit holder to submit to the floodplain administrator a certification of the elevation of the reference level, in relation to mean sea level. The floodplain administrator shall review the certificated data submitted. Deficiencies detected by such review shall be corrected by the permit holder prior to the beginning of construction. Failure to submit the certification or failure to make required corrections shall be cause to deny a floodplain development permit.
(b) An elevation certificate (FEMA Form 086-0-33) is required after the reference level is established. Within seven calendar days of establishment of the reference level elevation, it shall be the duty of the permit holder to submit to the floodplain administrator a certification of the elevation of the reference level, in relation to mean sea level. Any work done within the seven day calendar period and prior to submission of the certification shall be at the permit holder’s risk. The floodplain administrator shall review the certificate data submitted. Deficiencies detected by such review shall be corrected by the permit holder immediately and prior to further work being permitted to proceed. Failure to submit the certification or failure to make required corrections shall be cause to issue a stop-work order for the project.
(c) A final as-built elevation certificate (FEMA Form 086-0-33) is required after construction is completed and prior to certificate of compliance/ occupancy issuance. It shall be the duty of the permit holder to submit to the floodplain administrator a certification of final as-built construction of the elevation of the reference level and all attendant utilities. The floodplain administrator shall review the certificate data submitted. Deficiencies detected by such review shall be corrected by the permit holder immediately and prior to certificate of compliance/ occupancy issuance. In some instances, another certification may be required to certify corrected as-built construction. Failure to submit the certification or failure to make required corrections shall be cause to withhold the issuance of a certificate of compliance/occupancy.
(2) Floodproofing certificate.
(a) If non- residential floodproofing is used to meet the Regulatory Flood Protection Elevation requirements, a Floodproofing Certificate (FEMA Form 086-0-34), with supporting data, an operational plan, and an inspection and maintenance plan are required prior to the actual start of any new construction. It shall be the duty of the permit holder to submit to the Floodplain Administrator a certification of the floodproofed design elevation of the reference level and all attendant utilities, in relation to NAVD 1988. Floodproofing certification shall be prepared by or under the direct supervision of a professional engineer or architect and certified by same. The Floodplain Administrator shall review the certificate data, the operational plan, and the inspection and maintenance plan. Deficiencies detected by such review shall be corrected by the applicant prior to permit approval. Failure to submit the certification or failure to make required corrections shall be cause to deny a floodplain development permit. Failure to construct in accordance with the certified design shall be cause to withhold the issuance of a certificate of compliance/occupancy.
(b) A final Finished Construction Floodproofing Certificate (FEMA Form 086-0-34), with supporting data, an operational plan, and an inspection and maintenance plan are required prior to the issuance of a certificate of compliance/occupancy. It shall be the duty of the permit holder to submit to the Floodplain Administrator a certification of the floodproofed design elevation of the reference level and all attendant utilities, in relation to NAVD 1988. Floodproofing certificate shall be prepared by or under the direct supervision of a professional engineer or architect and certified by same. The Floodplain Administrator shall review the certificate data, the operational plan, and the inspection and maintenance plan. Deficiencies detected by such review shall be corrected by the applicant prior to certificate of occupancy. Failure to submit the certification or failure to make required corrections shall be cause to deny a floodplain development permit. Failure to construct in accordance with the certified design shall be cause to deny a certificate of compliance/occupancy.
(3) If a manufactured home is placed within Zone AE and the elevation of the chassis is more than 36 inches in height above grade, an engineered foundation certification is required per § 154.21.
(4) If a watercourse is to be altered or relocated, a description of the extent of watercourse alteration or relocation; a professional engineer’s certified report on the effects of the proposed project on the flood-carrying capacity of the watercourse and the effects to properties located both upstream and downstream; and a map showing the location of the proposed watercourse alteration or relocation shall all be submitted by the permit applicant prior to issuance of a floodplain development permit.
(5) Certification exemptions. The following structures, if located within Zone AE are exempt from the elevation/floodproofing certification requirements specified in items (a) and (b) of this subsection:
(a) Recreational vehicles meeting requirements of § 154.21;
(b) Temporary structures meeting requirements of § 154.21; and
(c) Accessory structures less than 150 square feet meeting requirements of § 154.21.
(D) A V-Zone certification with accompanying design plans and specifications is required prior to issuance of a floodplain development permit within coastal high hazard areas. It shall be the duty of the permit applicant to submit to the floodplain administrator said certification to ensure the design standards of this chapter are met. A registered professional engineer or architect shall develop or review the structural design, plans, and specifications for construction and certify that the design and methods of construction to be used are in accordance with accepted standards of practice for meeting the provisions of this chapter. This certification is not a substitute for an elevation certificate.
(E) Determinations for existing buildings and structures. For applications for building permits to improve buildings and structures, including alterations, movement, enlargement, replacement, repair, change of occupancy, additions, rehabilitations, renovations, substantial improvements, repairs of substantial damage, and any other improvement of or work on such buildings and structures, the Floodplain Administrator, in coordination with the Building Official, shall:
(1) Estimate the market value, or require the applicant to obtain an appraisal of the market value prepared by a qualified independent appraiser, of the building or structure before the start of construction of the proposed work; in the case of repair, the market value of the building or structure shall be the market value before the damage occurred and before any repairs are made;
(2) Compare the cost to perform the improvement, the cost to repair a damaged building to its pre-damaged condition, or the combined costs of improvements and repairs, if applicable, to the market value of the building or structure;
(3) Determine and document whether the proposed work constitutes substantial improvement or repair of substantial damage; and
(4) Notify the applicant if it is determined that the work constitutes substantial improvement or repair of substantial damage and that compliance with the flood resistant construction requirements of the NC Building Code and this chapter is required.
(‘85 Code, § 8-4.4b.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18; Am. Ord. 24-08, passed 6-18-24)
The floodplain administrator shall perform, but not be limited to, the following duties:
(A) Review all floodplain development applications and issue permits for all proposed development within special flood hazard areas to assure that the requirements of this chapter have been satisfied.
(B) Advise permittee that additional federal or state permits (wetlands, endangered species, erosion and sedimentation control, CAMA, riparian buffers, mining, etc.) may be required, and require that copies of such permits be provided and maintained on file with the floodplain development permit.
(C) Notify adjacent communities and the North Carolina Department of Crime Control and Public Safety, Division of Emergency Management, State Coordinator for the National Flood Insurance Program prior to any alteration or relocation of a watercourse, and submit evidence of such notification to the Federal Emergency Management Agency (FEMA).
(D) Assure that maintenance is provided within the altered or relocated portion of said watercourse so that the flood-carrying capacity is not diminished.
(E) Prevent encroachments into floodways and non-encroachment areas unless the certification and flood hazard reduction provisions of this chapter are met.
(F) Obtain actual elevation (in relation to mean sea level) of the reference level (including basement) and all attendant utilities of all new or substantially improved structures, in accordance with § 154.36(C).
(G) Obtain actual elevation (in relation to mean sea level) to which all new and substantially improved structures and utilities have been floodproofed, in accordance with § 154.36(C).
(H) Obtain actual elevation (in relation to mean sea level) of all public utilities in accordance with § 154.36(C).
(J) Where interpretation is needed as to the exact location of boundaries of the special flood hazard areas (for example, where there appears to be a conflict between a mapped boundary and actual field conditions), make the necessary interpretation. The person contesting the location of the boundary shall be given a reasonable opportunity to appeal the interpretation as provided in this subchapter.
(K) When base flood elevation (BFE) data has not been provided in accordance with § 154.05, obtain, review, and reasonably utilize any base flood elevation (BFE) data, along with floodway data or non-encroachment area data available from a federal, state, or other source, including data developed pursuant to this chapter, in order to administer the provisions of this chapter.
(L) When base flood elevation (BFE) data is provided but no floodway nor non-encroachment area data has been provided in accordance with § 154.05, obtain, review, and reasonably utilize any floodway data or non-encroachment area data available from a federal, state, or other source in order to administer the provisions of this chapter.
(M) When the lowest ground elevation of a parcel or structure in a special flood hazard area is above the base flood elevation, advise the property owner of the option to apply for a Letter of Map Amendment (LOMA) from FEMA. Maintain a copy of the Letter of Map Amendment (LOMA) issued by FEMA in the floodplain development permit file.
(N) Permanently maintain all records that pertain to the administration of this chapter and make these records available for public inspection.
(O) Make on-site inspections of work in progress. As the work pursuant to a floodplain development permit progresses, the floodplain administrator shall make as many inspections of the work as may be necessary to ensure that the work is being done according to the provisions of the local ordinance and the terms of the permit. In exercising this power, the floodplain administrator has a right, upon presentation of proper credentials, to enter on any premises within the jurisdiction of the community at any reasonable hour for the purposes of inspection or other enforcement action.
(P) Issue stop-work orders as required. Whenever a building or part thereof is being constructed, reconstructed, altered, or repaired in violation of this chapter, the floodplain administrator may order the work to be immediately stopped. The stop-work order shall be in writing and directed to the person doing the work. The stop-work order shall state the specific work to be stopped, the specific reason(s) for the stoppage, and the condition(s) under which the work may be resumed. Violation of a stop-work order constitutes a misdemeanor.
(Q) Revoke floodplain development permits as required. The floodplain administrator may revoke and require the return of the floodplain development permit by notifying the permit holder in writing stating the reason(s) for the revocation. Permits shall be revoked for any substantial departure from the approved application, plans, or specifications; for refusal or failure to comply with the requirements of state or local laws; or for false statements or misrepresentations made in securing the permit. Any floodplain development permit mistakenly issued in violation of an applicable state or local law may also be revoked.
(R) Make periodic inspections throughout all special flood hazard areas within the jurisdiction of the community. The floodplain administrator and each member of his or her inspections department shall have a right, upon presentation of proper credentials, to enter on any premises within the territorial jurisdiction of the department at any reasonable hour for the purposes of inspection or other enforcement action.
(S) Follow through with corrective procedures of this chapter.
(T) Review, provide input, and make recommendations for variance requests.
(U) Maintain a current map repository to include, but not limited to, the FIS Report, FIRM and other official flood maps and studies adopted in accordance with § 154.05, including any revisions thereto including Letters of Map Change, issued by FEMA. Notify state and FEMA of mapping needs.
(V) Coordinate revisions to FIS reports and FIRMs, including Letters of Map Revision Based on Fill (LOMR-F) and Letters of Map Revision (LOMR).
('85 Code, § 8-4.4c.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18)
(A) The Board of Adjustment as established by the town, hereinafter referred to as the “appeal board,” shall hear and decide requests for variances from the requirements of this chapter.
(B) Any person aggrieved by the decision of the appeal board may appeal such decision to the Court, as provided in G.S. Chapter 7A.
(C) Variances may be issued for:
(1) The repair or rehabilitation of historic structures upon the determination that the proposed repair or rehabilitation will not preclude the structure's continued designation as a historic structure and that the variance is the minimum necessary to preserve the historic character and design of the structure.
(2) Functionally dependent facilities if determined to meet the definition as stated in § 154.03, provided provisions of this chapter have been satisfied, and such facilities are protected by methods that minimize flood damages.
(3) Any other type of development provided it meets the requirements stated in this section.
(D) In passing upon variances, the appeal board shall consider all technical evaluations, all relevant factors, all standards specified in other sections of this chapter, and:
(1) The danger that materials may be swept onto other lands to the injury of others;
(2) The danger to life and property due to flooding or erosion damage;
(3) The susceptibility of the proposed facility and its contents to flood damage and the effect of such damage on the individual owner;
(4) The importance of the services provided by the proposed facility to the community;
(5) The necessity to the facility of a waterfront location as defined under § 154.03 as a functionally dependent facility, where applicable;
(6) The availability of alternative locations, not subject to flooding or erosion damage, for the proposed use;
(7) The compatibility of the proposed use with existing and anticipated development;
(8) The relationship of the proposed use to the comprehensive plan and floodplain management program for that area;
(9) The safety of access to the property in times of flood for ordinary and emergency vehicles;
(10) The expected heights, velocity, duration, rate of rise, and sediment transport of the floodwaters and the effects of wave action, if applicable, expected at the site; and
(11) The costs of providing governmental services during and after flood conditions including maintenance and repair of public utilities and facilities such as sewer, gas, electrical and water systems, and streets and bridges.
(E) A written report addressing each of the above factors shall be submitted with the application for a variance.
(F) Upon consideration of the factors listed above and the purposes of this chapter, the appeal board may attach such conditions to the granting of variances as it deems necessary to further the purposes of this chapter.
(G) Any applicant to whom a variance is granted shall be given written notice specifying the difference between the base flood elevation (BFE) and the elevation to which the structure is to be built and that such construction below the base flood elevation increases risks to life and property, and that the issuance of a variance to construct a structure below the base flood elevation will result in increased premium rates for flood insurance up to $25 per $100 of insurance coverage. Such notification shall be maintained with a record of all variance actions, including justification for their issuance.
(H) The floodplain administrator shall maintain the records of all appeal actions and report any variances to the Federal Emergency Management Agency and the State of North Carolina upon request.
(I) Conditions for variances:
(1) Variances shall not be issued when the variance will make the structure in violation of other federal, state, or local laws, regulations, or ordinances.
(2) Variances shall not be issued within any designated floodway or non-encroachment area if the variance would result in any increase in flood levels during the base flood discharge.
(3) Variances shall only be issued upon a determination that the variance is the minimum necessary, considering the flood hazard, to afford relief.
(4) Variances shall only be issued prior to development permit approval.
(5) Variances shall only be issued upon:
(a) A showing of good and sufficient cause;
(b) A determination that failure to grant the variance would result in exceptional hardship; and
(c) A determination that the granting of a variance will not result in increased flood heights, additional threats to public safety, or extraordinary public expense, create nuisance, cause fraud on or victimization of the public, or conflict with existing local laws or ordinances.
(6) A variance may be issued for solid waste disposal facilities or sites, hazardous waste management facilities, salvage yards, and chemical storage facilities that are located in special flood hazard areas provided that all of the following conditions are met:
(a) The use serves a critical need in the community;
(b) No feasible location exists for the use outside the special flood hazard area; and
(c) The reference level of any structure is elevated or floodproofed to at least the regulatory flood protection elevation.
(7) The use complies with all other applicable federal, state and local laws.
(8) The town has notified the Secretary of the North Carolina Department of Public Safety of its intention to grant a variance at least 30 calendar days prior to granting the variance.
(‘85 Code, § 8-4.4e.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 02-12, passed 10-14-02; Am. Ord. 03-01, passed 2-24-03; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18; Am. Ord. 21-10, passed 6-15-21)
As the work pursuant to a permit progresses, the local Building Inspector and Development Services Officer shall make as many inspections of the work as may be necessary to ensure that the work is being done according to the provisions of this chapter and the terms of the permit. In exercising this power, the Building Inspector and Development Services Officer has a right, upon presentation of proper credentials, to enter on any premises within the territorial jurisdiction at any reasonable hour for the purposes of inspection or other enforcement action.
(‘85 Code, § 8-4.4d.1.) (Ord. 31, passed - - ; Am. Ord. 5-87, passed 3-24-87; Am. Ord. 06-06, passed 5-22-06; Am. Ord. 18-13, passed 8-6-18; Am. Ord. 20-11, passed 9-3-20)