34-3-15   COMPACTION VERIFICATION.
    The developer shall be responsible for providing soils testing results to the Village Engineer to verify compliance with the above stated compaction requirements.
   (A)   In general, soils tests shall be taken every two hundred (200) feet, eight (8) feet off of the centerline; at intersecting streets; and at sag (low) points.
   (B)   A written report from a Registered Professional Engineer, certifying that soils throughout the embankment and subgrade material uniformly meet the compaction requirements, shall be provided to the Village at least twenty-four (24) hours prior to paving or pouring curb and gutter.