§ 54.23 TEST AND MAINTENANCE REPORTS.
   (A)   A backflow prevention assembly test and maintenance report on a form promulgated by the Director must be completed by the recognized tester for each assembly tested. The signed and dated original must be submitted to the Director within 10 working days after the testing is performed. The Director may authorize the use of a report format which differs from that found in this section if it minimally contains all information required by the promulgated form.
   (B)   The Director must retain test and maintenance reports for a minimum of 3 years, and must provide those records to Commission staff for inspection upon request.
(Ord. 2019-22, passed 8-13-19)