§ 4-103.   Schedule of Fees.
A schedule of fees for building permits shall be as established by resolution of the Township Council.
   A.   Township costs for plan examination and field inspections by the building inspector shall be paid or reimbursed by fees from the applicant for the building permit.
   B.   The Township Manager shall establish an escrow account for the receipt of all fees and payment of all charges of the Township building inspector with respect to plan examination and field inspections for building permit applications.
   C.   If any building permit application is withdrawn or modified before building inspector costs are incurred, any funds remaining in the said escrow account not necessary to reimburse building inspector costs shall be returned to the applicant.
(Ord. 2, § 2, 4-3-61; as amended by Ord. 8, 1, 2-4-63; by Ord. 212, 5-11-88; and by Ord. 352, 12-30-96)