§ 27-1303. Life of a Permit.
Any erection, construction, reconstruction, alteration or moving of a building or other structure authorized by a zoning permit shall be commenced and any change in use of a building or land authorized by a zoning permit shall be undertaken within six months after the date of issuance of the permit. However, in case of erection or construction of a building, the right to proceed with construction may be extended annually without payment of additional fees for an aggregate period of not more than 30 calendar months, provided that the construction pursuant to said permit has commenced within the first 6 month period. An Occupancy Permit shall expire at the same time as the Zoning Permit for the use, building, or structure to which the Occupancy Permit is applicable.
(Ord. 45, Z-§ 1303, 5/12/76; as amended by Ord. 103, § 5, 4/8/81)