§ 27-907. Time Limit On Construction Permit.
Permits issued pursuant to this Part shall expire within 1 year after date of issuance thereof, unless the approved project is completed, or unless the Township Council shall extend the permit for successive terms not exceeding one year each. In those cases where the original permit is issued and the construction schedule calls for a term of longer than one year, the permit shall be automatically renewed by the Zoning Officer for an additional one year period, subject to such safeguard as the Zoning Officer may prescribe in the public interest.
(Ord. 45, Z-§ 907, 5/12/76)