§ 165. General Requirements
   1.   Existing edges of flexible pavement shall be cut vertically and removed on a line not less than nine (9) inches on each side of and parallel to the trench opening and to a depth of seven (7) inches for restoration.
   2.   Restoration of pavements shall consist of five (5) inches of bituminous construction base course and two (2) inches of hot-mix bituminous concrete surface course (ID-2). Between November 1st and March 1st ID-2 shall not be laid except with the written permission of the Township Inspector.
   3.   The installation of underground electrical and/or telephone lines immediately behind concrete curbs (i.e., between curbs and sidewalks) shall require a street excavation permit.
   4.   All materials and workmanship shall comply with the Pennsylvania Department of Transportation, Form 408, dated 1976, with special attention to the following:
      Sections: 104.04   Traffic Maintenance and Safety
         107.25   Accessibility of Fire Hydrant
         107.12   Care of public and private property
         107.11   Barricades, danger, warning, and detour signs
         107.04   Restoration of surface opened by permit
         105.06   Public and private structures on the project
         701   Cement
         703   Fine & Course Aggregate
         210   Subgrade
         650   Shoulders
         350   Subbase
         601.3(d) Backfilling of trench & placing
         901 & 902 Maintenance & protection of traffic 300   Base Course
         400 & 500 Pavement & Surface Course