§ 158.06 UTILITY NOTIFICATION AND INTERCONNECTION.
   No grid-interconnected small wind energy system shall be installed, constructed or maintained until evidence has been given to the city that the appropriate utility provider has been informed of the owner’s intent to install a grid-connected customer-owned wind energy steam and that the customer’s system meets the utility’s approved specifications for interconnection. Off-grid systems shall be exempt from this requirement.
(Ord. O-2009-024, passed 8-25-09) Penalty, see § 158.99