13.08.060 Costs for additional facilities.
   A.   Whenever sewer service to a property requires construction of more than one hundred feet of off-site sewer line to the property, or construction of a sewer pump station or other unusual sewer facilities, these costs must be borne by the person or properties to be served.
   B.   However, if these additional facilities will potentially serve other properties, the city may enter into a reimbursement agreement to refund a portion of these costs. The refund amount will be based on the sewer connection fees received by the city. Reimbursement payments will be made based upon forty percent of the sewer capacity and collector fees received from properties served by the facilities included in the reimbursement agreement by the city within the fiscal year after completion and acceptance by the city, and each fiscal year thereafter.
   C.   The amount reimbursed by the city shall not exceed the amount specified in the reimbursement agreement. The agreement shall be for a period not to exceed ten years.
(Ord. 539 (part), 1988).