§ 12-5-3 CONSTRUCTION PLAN REVIEW PROCESS.
   (A)   After receiving approval of the preliminary plan, the subdivider shall submit three sets of construction plans to the Zoning Administrator who shall retain one set on file and distribute the remaining as follows:
      (1)   One set to the Village Engineer;
      (2)   One set to the County Superintendent of Highways when the subdivision is located outside the corporate limits of the village; and
   (B)   Construction plans shall be submitted a minimum of 30 calendar days before the final plat is to be submitted for review.
   (C)   The Village Engineer shall complete his or her review within 30 calendar days after all items of information required by § 12-4-2 have been submitted in writing.
   (D)   Within 30 calendar days after complete submission, the Village Engineer shall notify the subdivider’s engineer of approval of the plans or of any required changes unless the review time is extended for no more than 14 calendar days by the Village Engineer in a letter to the subdivider’s engineer listing reasons for the extension. If plans must be resubmitted, the Village Engineer shall also inform the engineer of the number of sets of plans to be submitted.
   (E)   When construction plans are resubmitted with the required changes, they shall be re-reviewed within 14 calendar days unless the review time is again extended by the Village Engineer in the manner set forth in division (D) above.
   (F)   The Village Engineer shall notify the subdivider’s engineer and the Planning Committee of the approval of the construction plans. Construction plans shall not be approved until proof of acquisition of a county access permit or 404 permit, if applicable, is submitted.
(Ord. 04-09, passed 9-21-2004)