35-40   Commencement Of Service
Before any water main which is constructed by a private person or entity and connected to the City water system will be accepted and service commenced, the following requirements must be met:
   A.   The water mains must pass all pressure tests required by the Utilities Department.
   B.   The water mains must pass all water quality tests required by the City of Grand Island or any state or federal agency.
   C.   The registered professional engineer must inspect and approve the water main and issue a certificate of completion attesting that the water mains were constructed in accordance with the water main construction plans and specifications.
   D.   The Public Works Director must accept the engineer's certificate of completion. (Amended by Ordinance No. 9533, effective 05-05-2015)