34-85   FCC Shot Clock Requirements
   A.   Eligible Facilities Request. This Section implements Section 6409(a) of the Spectrum Act, 47 U.S.C. Section 1455(a), as interpreted by the FCC in its Report and Order No. 14-153 and Declaratory Ruling and Third Report and Order released September 27, 2018 which requires a state or local government to approve any Eligible Facilities Request for a modification of an existing tower or base station that does not result in a substantial change to the physical dimensions of such tower or base station. Eligible Facilities Requests shall be governed by the provisions of Federal law including, but not limited to, application review, the sixty (60) day shot clock, tolling and deemed granted remedy.
   B.   Collocation for other than Small Wireless Facilities. This Section implements, in part, 47 U.S.C. Section 332(c)(7) of the Federal Communications Act of 1934, as amended, as interpreted by the FCC in its Report and Order No. 14-153 and Declaratory Ruling and Third Report and Order released September 27, 2018 regarding collocation applications for other than small wireless facilities including, but not limited to, application review, the ninety (90) day shot clock and tolling.
   C.   New Macro Cell Tower. This Section implements, in part, 47 U.S.C. Section 332(c)(7) of the Federal Communications Act of 1934, as amended, as interpreted by the FCC in its Report and Order No. 14-153 and Declaratory Ruling and Third Report and Order released September 27, 2018 regarding new macro cell tower applications including, but not limited to, application review, the one hundred fifty (150) day shot clock and tolling.
   D.   Small Wireless Facilities - Collocation on Existing Structures. This Section implements the shot clock procedures that are contained in the Declaratory Ruling and Third Report and Order released September 27, 2018, regarding the collocation of small wireless facilities on existing structures, including but not limited to application review, the sixty (60) day shot clock, resetting the sixty (60) day shot clock once the City timely sends a notice of an incomplete application and tolling.
   E.   Small Wireless Facilities - New Structure. This Section implements the shot clock procedures that are contained in the Declaratory Ruling and Third Report and Order released September 27, 2018, regarding the construction of small wireless facilities on a new structure, including but not limited to application review, the ninety (90) day shot clock, resetting the ninety (90) day shot clock once the City timely sends a notice of an incomplete application and tolling.