A. All poles for supporting small wireless facilities in the right-of-way are permitted only after applying the following siting priorities, ordered from most-preferred (1) to least-preferred (6):
1. existing street lights;
2. relocated street lights;
3. replacement of street lights (with a pole of dual functionality) at the same location that can structurally support the Small Wireless Facilities;
4. new poles in the right-of-way specifically for Small Wireless Facilities;
5. electric distribution poles if they can meet the pole attachment agreement requirements;
6. traffic control signals but they must show why none of the other choices will work and ensure that the provider’s equipment will not interfere with the functionality of the traffic signals.
B. The applicant for a pole shall address preferences 4-6 in an alternative sites analysis prepared pursuant to §34-80 below.