1165.03 REGULATIONS FOR TOPSOIL REMOVAL.
   Any person, firm, corporation or other entity desiring to remove topsoil, loam, sand, gravel, rock, stone, clay and other similar substances from land located in any area or place within the Village, shall comply with the following regulations.
   (a)   Whenever topsoil or loam is to be removed from land within the Village, a minimum of four (4) inches of topsoil shall remain or be replaced above the subsoil, clay or other unproductive grounds after completion of the operation. The removal, stockpiling, or replacement of the soil shall comply with other applicable regulations to prevent surface run-off.
   (b)   A grading permit and storm water pollution prevention plan shall be approved as part of this activity.
      (Ord. 2016-07-24. Passed 8-3-16.)