10-1-8-1: FEES ESTABLISHED:
   A.   Permit Costs: The following work, when performed individually and not as part of a larger overall work scope, shall be charged a fixed fee, as set forth below:
      1.   Residential - single-family:
Permit
Cost
Permit
Cost
Balcony (replacement)
$ 75.00
Burglar alarm
50.00
Deck (covered or uncovered)
100.00
Demolition (interior)
50.00
Door replacement
50.00
Electric (minimum)
50.00
Electric panel
75.00
Fence
50.00
Fireplace - prefab
100.00
Flagpole
75.00
Generator
75.00
Lawn irrigation
75.00
Mechanical:
 
Minimum
50.00
Air conditioning
50.00
Furnace
50.00
Furnace and A/C
75.00
Water heater
50.00
Pavement:
 
Private - driveway, patio, service walk
50.00
Public - sidewalk, apron
50.00
Private and public
75.00
Plumbing - 3 fixtures or less (minimum)
50.00
Additional charge per fixture over 3
5.00
Roof with prepermit inspection
75.00
Roof without prepermit inspection
50.00
Shed/gazebo (on ground)
50.00
Shed/gazebo (on slab)
75.00
Siding with prepermit inspection
75.00
Siding without prepermit inspection
50.00
Swimming pool/hot tub/spa - (aboveground)
75.00
Utility connection - water or sewer
50.00
Utility disconnection - water or sewer
50.00
Window replacement (1-5)
50.00
Window replacement (6)
75.00
 
      2.   Commercial/industrial/office/multi-family:
Permit
Cost
Permit
Cost
Construction/sales trailer
$100.00
Elevator
100.00
Fire alarms
75.00
Fire sprinklers
100.00
Irrigation system
125.00
Pavement replacement:
 
Multi-family
75.00
<1,000 square feet
100.00
>1,000 square feet
150.00
Pavement - sealcoat and stripe
75.00
Security alarm
75.00
Sign:
 
Change of copy only
50.00
Monument
100.00
Illuminated monument
125.00
Temporary
75.00
Wall
75.00
Illuminated wall
100.00
Temporary electric service
75.00
Temporary use
100.00
Utility connection - water and sewer
100.00
Utility disconnection - water and sewer
100.00
Water heater (not boiler)
75.00
 
   B.   Permit Costs Based On Value Of Construction/Improvement: Fees for building permits, not specifically listed in subsection A of this section, shall be assessed based on the market value of the construction or improvement to be completed.
      1.   Market Value: The market value shall be determined based upon the values stated in either, "Means Square Foot Costs", or "Building Construction Cost Date", as published by R.S. Means Company, Inc. (Kingston, Massachusetts), as amended from time to time, which said publications are hereby adopted by reference by the village of Glendale Heights. In lieu of using this publication, the village, at its sole and exclusive discretion, may accept the value listed on a signed contract between the permit applicant and their contractor(s), or an estimate of probable construction cost, signed and sealed by a registered architect or engineer.
      2.   Permit Fee: 1.5 percent of estimated construction/improvement cost, but not less than the sum of the minimum fees of all applicable trades.
   C.   Special Projects: There are certain special projects where the cost of construction does not accurately reflect the cost of plan review and inspection to the village. In these instances, permit fees will be based on the hourly rate of plan review and inspection services, as determined from time to time by the village of Glendale Heights.
      1.   Special projects include, but are not limited to, the following construction:
         a.   Demolition.
         b.   Inground swimming pools.
         c.   Site alteration including grading and utility installation on private property.
         d.   Cellular tower construction and/or modification.
   D.   Miscellaneous Provisions:
      1.   Reinspection And Phased Inspection Fee: Inspection fees shall be included in the building permit fee, along with one reinspection. Additional reinspections due to failure, request for phasing or not being present at the scheduled inspection time will be charged a reinspection fee as listed below:
 
Residential
$25.00
Nonresidential
50.00
 
      2.   Expedited Real Estate Transfer Inspection: In accordance with section 10-14C-4 of this title, real estate transfer inspections shall be scheduled a minimum of twenty one (21) days prior to transfer. An applicant may request an expedited inspection less than twenty one (21) days prior to transfer at double the standard inspection fee. The village will schedule the inspection, if it can accommodate the request, but is not obligated to do so. Payment of the fee is required prior to scheduling the inspection.
      3.   Consulting Services: The village, at its sole discretion, may determine that it is necessary to hire a consultant to provide professional services, including, but not limited to, plan reviews, inspections and legal review. An applicant shall be responsible for payment of these costs as part of the permit fee. If an applicant withdraws a permit application, he/she shall be responsible for any and all consultant fees incurred.
      4.   Consulting Services Fees: For any project that the village has determined consulting services are required, the following deposit shall be submitted with the building permit application:
 
Projects which include architectural, structural and/or MEP plans
$1,500.00
Projects which include civil engineering plans
1,500.00
 
If the deposit is depleted, the applicant shall submit an additional deposit to offset additional consulting services. Any remaining balance shall be refunded after a final certificate of occupancy is issued.
      5.   Field Change Permit: Whenever a substantive change in the scope of work is proposed subsequent to approval of the permit application, a field change permit application shall be submitted, along with such construction documents as are necessary to allow a comprehensive review of the potential impact of the proposed change. The valuation used to determine permit fees shall equal the value of the proposed new scope of work (example: If $10,000.00 worth of lighting is eliminated from a project, and $8,000.00 worth of alternative lighting is substituted, the valuation is $8,000.00). The minimum permit fee shall be fifty dollars ($50.00) for residential construction and one hundred dollars ($100.00) for commercial construction.
      6.   Failure To Obtain A Permit: Commencing construction on work that requires a permit without having obtained a permit is a violation of this code. Any person found to have violated this provision of this code shall be assessed additional permit fees in accordance with the following:
         Calculated permit fee + 100% additional permit fee
The calculated permit fee shall include plan review, inspection, and development fees, but shall exclude expedited plan review and/or inspection, which will be charged separately according to the method for each process.
      7.   Renewal Of Suspended Permit: An applicant may submit a written request to renew a suspended permit once. A permit may be renewed only if: a) the project scope does not change, and b) a code amendment would not impact the project. The permit fee for a permit renewal shall be fifty percent (50%) of the original permit fee.
      8.   Phased Permits:
         a.   An applicant may submit a written request to have a proposed development considered in phases. The following phased permits may be issued provided that all of the submittal criteria are met:
            (1)   Mass grading.
            (2)   Site development.
            (3)   Foundation.
            (4)   Shell.
            (5)   Phased occupancy.
         b.   If and when the village, at its sole and exclusive discretion, determines that the criteria for issuance of a phased permit have been met, an applicant shall execute a hold harmless agreement before a phased permit may be issued.
         c.   The permit fee for a phased permit shall be based upon the value of the scope of the work proposed, plus ten percent (10%) to cover the village's additional administrative expenses.
      9.   DuPage County Receipt Of Payment: No building permit or occupancy permit shall be authorized for constructing, enlarging or altering any building or structure until the village has received a copy of a receipt of payment of the fees imposed by the county fair share transportation impact fee ordinance.
      10.   Temporary Certificate Of Occupancy: The fee for a temporary certificate of occupancy shall be as follows:
 
Residential - single-family
$50.00
Commercial/industrial/office/multi-family
100.00
 
      11.   Written Zoning Verification: The fee for a written zoning verification shall be one hundred dollars ($100.00).
      12.   Irrevocable Letter Of Credit: Prior to issuance of a building permit, an applicant shall be required to provide an irrevocable letter of credit or similar security for a sum equal to one hundred twenty five percent (125%) of an approved estimate of construction cost for the site development work scope, including public improvements, stormwater management, erosion control and permanent stabilized landscaping. (Ord. 2014-51, 8-21-2014)