The Owner/Developer who desires to subdivide or develop any land subject to this Ordinance shall provide and pay the entire cost of improvements to such land as follows:
(a) Streets and parking areas, graded full width and paved, including drainage structures, bridges, sidewalks (including provisions for handicapped access as may be required by ADA), curbs and other improvements as may be required by these regulations and/or the City Standard Plans and Specifications.
(b) Sanitary sewers, including manholes, services and all appurtenances.
(c) Water distribution system including mains, services, valves, fire hydrants and all appurtenances.
(d) Storm drainage improvements, including both enclosed and non-enclosed systems, as well as all appurtenances to such systems.
(e) Monuments, stakes and property pins.
(f) Street signs designating the name of each street at each intersection within the development and other traffic control signage as determined necessary by the City Engineer.
(g) Street lighting including poles, underground conduits and appurtenances;
(h) Utilities, including electric, telephone and cable television services.
(i) All other improvements shown on the plans as approved by the City.
The Owner/Developer shall provide for the future extension of streets and water, sanitary sewer and storm drainage lines from his/her site to adjacent property as deemed necessary by the Planning Commission.
(Ord. 2009-85. Passed 12-8-09.)
The Owner/Developer of the land being developed shall be subject to the following obligations:
(a) The Owner/Developer shall be responsible for the payment of all fees incurred by the City Engineer pertaining to administrative responsibilities specified in this Ordinance, including inspection of the improvements
(b) All construction work and materials used in connection with improvements shall conform to the requirements of the City and be installed under the general supervision of the City Engineer.
(c) The Owner/Developer, or his agent, shall give not less than three (3) working days notice to the City for any inspection to be conducted. The Owner/Developer shall also insure that no work shall be covered or obscured prior to inspection by the City.
(d) The Owner/Developer shall provide proof of insurance and hold the City free and harmless from any and all claims for damage of every nature arising or growing out of the construction of improvements or resulting from improvements and shall defend, at his own cost and expense, any suit or action brought against the City by reason thereof.
(e) All improvements and utilities will be satisfactorily installed within one (1) year from the date of approval of the Construction Plans or within such other time schedule as specifically approved by the City Engineer.
(f) As an alternative to the construction and approval of the required public improvements prior to recording the final plat, an acceptable performance assurance equal to one-hundred ten percent (110%) of the estimated cost of all required improvements, as approved by the City Engineer, shall be deposited with the City. Such performance assurance shall consist of one of the following:
(1) A performance or construction bond equal to one hundred ten percent (110%) of the estimated construction cost as approved by the City Engineer for the public improvements. Such bond shall be without time limit and shall be on such forms as provided by the City, or
(2) A letter of credit or certified check made payable to the City. equal to one hundred ten percent (110%) of the estimated construction cost as approved by the City Engineer for the public improvements.
(g) All permits and approvals shall be obtained and all fees and deposits paid prior to beginning any construction of any improvements;
(h) During construction and prior to acceptance of any public improvement, the Owner/Developer shall remove or cause to be removed such dirt and debris and foreign matter from all public rights of way, improvements and/or easements as were deposited, left or resulted from the construction of improvements of any nature within the development. Such removal shall take place within twenty-four (24) hours after being notified by the City that such work is required, and shall be completed to the satisfaction of the City Engineer.
(i) All public improvements shall be guaranteed by the Owner/Developer for a period of one (1) year from the date such improvement is accepted, in writing, by the City. Such guarantee shall consist of a maintenance bond, certified check or other acceptable instrument, for ten percent (10%) of the total cost of the improvements. Such guarantee shall include any and all defects and deficiencies in workmanship and materials. The cost of all labor, materials, equipment and other incidentals required to maintain, repair and replace any or all of such improvements and to maintain them in good and proper condition, excluding ordinary wear and tear, but including filling trenches and restoring lawns, sidewalks, yards, streets, sewers, pipe lines, etc., during the one year guarantee period shall be assumed by such Owner/Developer. In the event the Owner/Developer fails to make such maintenance, repairs or replacements within a reasonable time after notice in writing by the City, or in the event of an emergency which may endanger life or property, the City may make or cause to be made, such repairs or replacements from the above guarantee.
(j) The Owner/Developer shall execute a development agreement with the City, specifying the terms and conditions required under this Section of this Ordinance.
(k) The Owner/Developer shall furnish to the City final plats and as-built drawings of all improvements as required by these regulations.
(l) No person or owner shall violate any of the regulations established in this Section and, upon identifying such violation, the City shall have the authority to:
(1) Stop all work on the development site forthwith;
(2) Hold the bonding company responsible for the completion of the public improvement according to the approved construction drawings and the agreement.
(Ord. 2009-85. Passed 12-8-09.)
In consideration for the agreement by the Owner/Developer of the land being developed to install utilities and/or streets to sizes and configurations in excess of the needs of the land being developed, the City shall share in the cost of the excess size and configuration of the utilities and/or streets as stipulated herein:
(a) A utility or street shall be considered excessive to needs of the land being developed when any of the following conditions exist:
(1) The City specifically requires a greater width, size or configuration of any nonadjacent street for the purpose of meeting the future needs of the City as provided for a comprehensive or thoroughfare plan, or similar study, as adopted by City Council;
(2) There is additional pavement width and depth and/or additional length of storm sewers and other improvements required for all thoroughfares;
(3) The City requests that a water line be more than twelve inches (12") in diameter, when such size is not required to meet the needs of the land being developed;
(4) A sanitary sewer line is more than fifteen inches (15") in diameter, unless this size is required for the land being developed by reason of grade or trench loading requirements of the land being developed, or because of anticipated sewerage flows from the land being developed;
(5) Other conditions warrant cost sharing and such conditions are approved by City Council.
(b) The City shall share in the cost of improvements by:
(1) Paying for all the material costs only for the size difference of the waterline, sanitary sewer pipe and the appurtenances thereto between what is required for the land being developed and what is excessive to the needs of the land being developed;
(2) Paying for all materials F.O.B. the plant, factory, supply depot or warehouse for such other improvements that are excessive to the land being developed;
(c) Nothing in this Section shall be interpreted, read or construed to obligate the City for expenses incurred by the Owner/Developer, contractor, subcontractor or other persons because of:
(1) Equipment or labor costs, including but not limited to excavation, due to the over sizing and/or increased depth or width of waterlines, sewers and/or roadways;
(2) Equipment, labor or material cost due to improperly and/or unacceptable installed improvements including the removal and replacement thereof; or
(3) Any improvements installed prior to the approval of the cost sharing by the City.
(d) Upon approval by Planning Commission of the preliminary plat for the land being developed, the following procedure shall be followed:
(1) The City Engineer shall identify all improvements eligible for cost sharing, and shall estimate the cost of the City's portion of such improvements;
(2) If applicable, an ordinance shall be submitted to Council for approval, appropriating funds to cover the City's portion;
(3) Upon completion and acceptance of the work and quantities thereof by the City Engineer, the costs shall be certified to the chief fiscal officer of the City.
(e) Failure of the Owner/Developer of the land to provide the City with copies of billings, invoices, contracts, agreements or such other evidence of construction costs as the City Engineer deems necessary within six (6) months of completion and acceptance of the improvements by the City, shall constitute just cause to declare the City's agreement to cost share as provided herein null and void and no reimbursement shall be made or monies paid without reapproval by Council.