§ 50.22  TEMPORARY SERVICE.
   (A)   An applicant for temporary service shall be required to pay a fee of $200 for the cost of labor and material required for supplying and connecting the temporary service, for discontinuing and removing the service equipment, and for the supervision, use of tools, and indirect costs, in accordance with the job work order procedure of the utility.
   (B)   The utility may require a suitable deposit to insure payment of the fee set forth above plus the charges for energy consumed. No temporary installation may continue for a period of more than 12 months, unless the installation conforms to the requirements of permanent installation.
('75 Code, § 6.32)  (Am. Ord. 16-17, passed 11-14-16)  Penalty, see § 10.99