§ 51.098 QUAIL RUN SEWER EXTENSION DEVELOPMENT FEE.
   (A)   All connections to the Quail Run sewer extension, within the crosshatched area on the Quail Run Sewer Extension Service Area Map attached to Ord. No. 346-04 and on file in the office of the Town Clerk, whether direct or indirect, will be subject to the Quail Run sewer extension development fee.
   (B)   The Quail Run sewer extension per acre development fee shall be paid at the time the building permit is issued. No connection shall be permitted until payment has been received by the town.
   (C)   The funds collected will be placed in a restricted “major sewer line account” and can only be used to install future major trunk, interceptor, extension or relief services.
   (D)   The charge will be based on the following fee schedule:
      (1)   The town will construct an eight-inch sewer line extension to provide sewer service to the Quail Run sewer extension service area. This plan provides for reimbursements to the town for the costs incurred in building the line plus or minus an adjustment for construction cost changes.
      (2)   A total charge as determined by the Town Manager will be expended to construct the Quail Run sewer extension, which includes construction costs, engineering costs, inspection costs and incidental costs.
      (3)   The service area for the Quail Run sewer extension, as shown in the crosshatched area of the map referenced in division (A) of this section, comprised 48.67 net acres defined as the gross acreage minus existing dedicated rights-of-way for streets, highways and canals. Any development within the service area that does not receive sewer service from the Quail Run sewer extension shall not be charged this development fee and likewise any development outside the service area that receives sewer service from the Quail Run sewer extension shall be charged this fee.
      (4)   The base reimbursement shall be as follows:
         Acreage Subject to Permit Request x Total Base Cost = Reimbursement
         48.67 (Net acreage)
      (5)   The actual reimbursement for the Quail Run sewer extension shall be adjusted to reflect the then current prevailing market rate for construction. The index rate for the adjustment shall be the Engineering News Record Index using March, 1994, as the base rate. The March, 1994, Index value of $5,381 shall be used in the calculation as follows:
         Base Reimbursement x (ENR Cost Index) = Actual reimbursement for permit
         $5,381 to issue.
(Prior Code, Ch. 18, Art. III, § 18-187.1) (Ord. 346-04, passed 6-21-2004)