§ 50-109  TIME FOR STARTING AND COMPLETING CONSTRUCTION.
   In accepting a plan for review under § 50-108, the Planning Commission shall be satisfied that the proponents of the integrated shopping center into to start construction within two years if a neighborhood shopping center and three years if a community shopping center from the date of the approval of the project and necessary district change, and intend to complete it within a reasonable period of time as determined by the Planning Commission.
(Ord. 2046, passed 4-11-1968)