5-307:   PERMIT REQUIRED FOR ELECTRICAL INSTALLATION; EXCEPTIONS; FEE:
   A.   Where the cost of the work exceeds One Hundred Fifty Dollars ($150.00), it is unlawful for any person to install any electrical wiring, fixtures, equipment or apparatus in or on any building or structure in the corporate limits of this city, change the electrical service entrance, or make extensions to any existing electrical installations without first securing a permit from the city clerk where the cost of work is One Hundred Fifty Dollars ($150.00) less, a permit must be obtained only if the electrical service entrance to a structure is changed.
   B.   Applications for electrical permits shall be made to the city clerk. The applicant shall provide such plans, specifications and other data as may be necessary to determine whether the permit shall be issued.
   C.   It is the duty of the electrical inspector or city clerk to issue all permits, and the electrical inspector to make inspection of all work for which permit has been issued within forty-eight (48) hours after having been notified that work is ready for inspection (Sundays and holidays not included).
   D.   No permit shall be issued until the applicant shall have paid a permit fee in such sum as set by the city council by motion or resolution. (Ord. 82-11-1, 11-1-1982)