1391.09 CONDITIONS REQUIRED DURING DEMOLITION.
   In addition to the requirements set forth in Sections 1391.06 and 1391.13, the following conditions shall be maintained during the course of demolition:
   (a)   The area shall be kept dust-free using covered shutes, etc. in disposing and hauling away of debris;
   (b)   The area shall be cleaned of debris periodically to prevent accumulation causing hazardous and unhealthful conditions;
   (c)   Working conditions and equipment for laborers shall be in accordance with the laws of the State governing demolition of buildings;
   (d)   Adequate protective measures shall be provided during demolition.
   (e)   All storm and sanitary laterals shall be plugged prior to the demolition of the building. These connections must be plugged in the City right of way unless approval is obtained from the City Engineer's office. All plugged connections must be inspected and approved by the City Engineer's office, prior to the demolition of the building.
   (f)   Any abandonment of water service lines shall comply with applicable statutes, rules and regulations, including, the Rules, Regulation and Policies of Elyria Public Utilities. For this subsection (f), the Building Inspector or the Superintendent of Water Distribution are authorized to impose a stop order when, in their opinion, there exists a hazard to the City's water distribution system. Work shall not resume until the Building Inspector or the Superintendent of Water Distribution withdraws the stop work order.
   The Building Inspector and the Health Commissioner of the City are authorized to impose a stop work order when, in their opinion, the requirements of this section are not being complied with. Work shall not be resumed until the Building Inspector or Health Commissioner withdraws the stop work order.
(Ord. 4878. Passed 9-16-57; Ord. 73-322. Passed 12-27-73; Ord. 2009-80. Passed 3-2-09.)