The Mayor is hereby authorized, as the contractual officer of the City, to review, approve and order modifications and changes to contracts for public improvement awarded under competitive bidding, provided that the net total increase of all change orders on any one contract for public improvements does not exceed ten percent of the original contract, or one hundred thousand dollars ($100,000), whichever is less; for the Chestnut Commons Connector Drive Improvement Project only, commencing in the year 2020, the not-to-exceed amount for purposes of this section shall be two hundred fifty thousand dollars ($250,000) due to the accelerated schedule and quick completion incentive clause of said project contract. No change order shall be ordered that would change the general purpose of the work being done, without specific Council approval.
(Ord. 82-82. Passed 4-19-82; Ord. 2008-100. Passed 7-7-08; Ord. 2020-78. Passed 7-6-20.)