§ 97.018 INSPECTION.
   (A)   Underground work. The excavation contractor in charge of the work must notify the City Engineer or designated inspector at least 2 hours before the work is ready for inspection. All work must be left uncovered and convenient for examination until inspected and approved. No notice shall be made for inspection until the work is entirely ready for thorough inspection.
   (B)   Road/surface work. Upon completion of the restoration and repair of the surface in the public right-of-way, the excavation contractor shall notify the City Engineer. If the City Engineer, upon the inspection of the completed work, determines that the restoration and repair has not been properly done in accordance with §§ 97.015 and 97.016, he shall request that the applicant making the excavation to do whatever may be necessary to cause said repair and restoration to comply with the provisions of this subchapter within 15 working days. The contractor shall maintain the restoration and repair for a period of 2 years. Failure to comply with these requirements shall cause the applicant to be in violation of this subchapter and subject to the penalties as set forth in § 97.999. In addition, said repair and restoration shall be made by the city and the cost thereof paid by the applicant.
(Ord. 5192, passed 11-16-2009)