1. Without first obtaining a street access permit from the Borough:
A. No driveway, local street or drainage facility or structure shall be constructed or altered within a Borough street right-of-way;
B. No property abutting or having ingress or egress via a Borough public street shall change its use or increase its daily peak traffic to a Borough street;
C. No drainage facility of the Borough shall be altered or a connection made thereto without first obtaining a permit from the Borough.
2. The applicant shall submit permit application in writing to the Borough Engineer or his designee in the form prescribed by this Part. The permit application shall be signed by property owner and accompanied by proof of ownership.
3. The application shall include plans detailing location and pertinent dimensions of proposed installation and existing street features and drainage control plans as required by § 21-704. The permit fee, in an amount as established from time to time by resolution of Borough Council, shall be submitted with the application.
4. Borough Engineer or his designee shall review all applications and plans for street or road construction which would adjoin or connect with any street within the boundaries of the Borough.
5. Subdivision and/or land development plan approval by the Borough Council under the Borough Subdivision and Land Development Ordinance shall operate as a street access permit approval under this section provided that:
A. The subdivision and/or land development plan complies with the requirements of this Part;
B. The applicant applies for and obtains a zoning use permit and a zoning occupancy permit from the Zoning Officer under the Borough Zoning Ordinance [Chapter 27]; and
C. The applicant complies with any and all conditions of approval of the subdivision and/or land development plan approval imposed by the Borough Council in accordance with the Borough Subdivision and Land Development Ordinance [Chapter 22].
(Ord. 966, 10/13/2022)