(a) Construction sites shall be enclosed by a security fence at all times from the commencement of any construction activities on the construction site, including, but not limited to, the delivery and/or storage of construction materials and equipment, until all of the following construction activities, if applicable, have been completed on the construction site:
(1) Demolition of existing structures;
(2) Excavating, backfilling and earthmoving;
(3) Exterior storage of construction materials, equipment, vehicles, spoil or stockpiles;
(4) Completion of building construction to the point where all buildings on the site are enclosed and secured against unauthorized entry.
(b) Security fencing shall be chainlink or solid fencing with a height of not less than six feet (6'). Fencing shall be maintained along the full perimeter of the construction site or, with the approval of the director, to a smaller portion of the construction site where all of the above described construction activities will be confined to that part of the construction site. (Ord. 0-04-05, 1-20-2004)
(c) The security fence shall be provided with an access gate, which shall be securely locked at the end of each workday day and at all times when work is not being done on the construction site. Applicant shall pay a locking service fee in the amount as set forth in the annual fee resolution adopted by the corporate authorities to the village for each occasion on which the gate is left unlocked and the village locks or otherwise secures the gate against unauthorized access. In addition, each such violation shall result in a one day stop work order. (Ord. 0-12-36, 10-1-2012)
(d) The applicant shall submit a site plan for approval by the director depicting the location of the security fencing and the tree protection fencing on the construction site at the same time as plans are submitted for permit approval for the site. (Ord. 0-04-05, 1-20-2004)