(a) No grading of a site shall be performed until the owner of the site has completed the appropriate unit of the building permit application, submitted supporting documentation and been issued a permit approving a stormwater drainage plan for the site. A stormwater drainage plan is required for the issuance of a permit.
(b) A permit shall not be required for routine and ordinary landscape activities, provided that such grading or landscape activities do not result in a material change in the volume, rate and pattern of stormwater runoff onto or off of the site.
(c) A separate permit is not required when a stormwater drainage plan is approved with a building permit issued for a site. The stormwater drainage plan must be submitted to and approved by the village engineer, prior to building permit issuance. (Ord. 0-09-09, 4-20-2009)