1. The low impact development practices provided in the BMP Manual and in Appendix 23-B of this Chapter shall be utilized for all regulated activities to the maximum extent practicable.
2. Stormwater runoff volume controls shall be implemented using the design storm method or the simplified method. For regulated activities equal to or less than 1 acre, this Chapter establishes no preference for either method; therefore, the applicant may select either method on the basis of economic considerations, the intrinsic limitations on applicability of the analytical procedures associated with each methodology, and other factors.
A. The design storm method (CG-1 in the BMP Manual) is applicable to any sized regulated activity. This method requires detailed modeling based on site conditions.
(1) Do not increase the post-development total runoff volume when compared to the pre-development total runoff volume for the 2-year/24-hour storm event.
(2) For hydrologic modeling purposes:
(a) Existing non-forested pervious areas must be considered meadow (good condition) for pre-development hydrologic calculations.
(b) Twenty percent of existing impervious area, when present on the proposed project site, and contained within the new proposed limit of disturbance, shall be considered meadow (good condition) for pre- development hydrologic calculations for re-development.
B. The simplified method (CG-2 in the BMP Manual) is independent of site conditions and should be used if the design storm method is not followed. This method is not applicable to regulated activities greater than 1 acre. For new impervious surfaces:
(1) Stormwater facilities shall capture at least the first 2 inches of runoff from all new impervious surfaces.
(2) At least the first 1 inch of runoff from new impervious surfaces shall be permanently removed from the runoff flow, i.e., it shall not be released into surface waters of the Commonwealth. Removal options include reuse, evaporation, transpiration, and infiltration.
(3) Wherever possible, infiltration facilities should be designed to accommodate infiltration of the entire permanently removed runoff; however, in all cases at least the first 0.5 inch of the permanently removed runoff should be infiltrated.
3. All applicable worksheets from Chapter 8 of the BMP Manual must be used when establishing volume controls.
4. Actual field infiltration tests at the location of the proposed elevation of the stormwater BMPs are required when 5,000 square feet or greater of new impervious surface is added. Infiltration test shall be conducted in accordance with BMP Manual. The Municipality shall be notified 24-hours prior to infiltration tests being conducted as to provide an opportunity for the Municipality to witness the tests.
(Ord. 11-01, 2/8/2011, §303)