(a) The Building Commissioner shall authorize the issuance of permits required by this Building and Housing Code and shall collect the fees therefor in accordance with the following schedule. All fees shall be paid to the Village through the Building Department when the permits are granted and shall be paid for by the owner of the building, the contractor(s), or the occupant. Council may abate some or all of the building permit fees in particular circumstances upon a determination that those fees would unreasonably inhibit the development of property.
(1) Residential fees shall be as follows:
Additional fees of 1% shall be added to all fees listed below for the Ohio Board of Building Standards
|
Additional fees of 1% shall be added to all fees listed below for the Ohio Board of Building Standards
| ||
Building Permits | ||
Plan review | $75.00 per hour | |
New dwelling (single dwelling) | $0.50 per sq. ft., $600.00 minimum | |
New dwelling (multiple units) | Same as single dwelling | |
Dwelling addition | $0.50 per sq. ft.. $200.00 minimum | |
Dwelling alteration | $0.50 per sq. ft., $100.00 minimum | |
Accessory building (new or addition) | $0.50 per sq. ft., $50.00 minimum | |
Accessory building (alteration) | $0.50 per sq. ft. | |
Demolition - dwelling | $200.00 | |
Demolition - accessory building | $50.00 | |
Retaining wall | $50.00, plus Engineer review fee | |
Patio/deck/porches | $0.50 per sq. ft.; $50.00 minimum | |
In-ground pools | $100.00 | |
Above ground pools | $50.00 (serves three dwelling or less); $100.00 (serves more than three dwelling) | |
Solar Panels | $1.00 per square foot ($100.00 minimum) | |
Re-inspection (after first re-inspection) | $50.00 each | |
Waterproofing | $50.00 | |
Exterior siding (more than 200 sq. ft.) | $50.00 | |
Windows and doors | $10.00 each | |
Electrical | ||
Plan review | $70.00 per hour | |
Temporary power pole | $50.00 | |
Electrical service | $50.00 | |
Sub panel | $50.00 | |
Generator | $50.00 | |
Electric furnace/heat pump (inside unit) | $50.00 | |
Miscellaneous electrical | $50.00 | |
Re-inspection (after first re-inspection) | $50.00 | |
HVAC | ||
Plan review | $70.00 per hour | |
Furnace (new or replacement) | $50.00 | |
A/C (new or replacement) | $50.00 | |
Hydronic - hot water or steam (new, replacement, extension) | $50.00 | |
Re-inspection (after first re-inspection) | $50.00 each | |
Plumbing | ||
Plan review | $70.00 per hour | |
Hot water tank (new or replacement) | $50.00 | |
Lawn irrigation system | $50.00 | |
Main water line | $50.00 | |
Sewage ejector pump | $50.00 | |
Miscellaneous plumbing | $50.00 | |
Re-inspection (after first re-inspection) | $50.00 | |
Miscellaneous Fees | ||
Driveway apron (new or replacement) | $50.00 | |
Driveway (total new or replacement, or repair more than 10 sq. ft.) | $50.00 | |
Patio, garage base, accessory building base, other concrete (new or replacement) | $50.00 | |
Fences | $0.20 per linear foot; $20.00 minimum | |
Street opening permit | $100.00 | |
Fireplace/chimney | $50.00 | |
Roofing | $50.00 | |
Exterior siding (more than 200 sq. ft.) | $50.00 | |
Re-inspection (after first re-inspection) | $50.00 | |
(2) Nonresidential (including retail, commercial, and industrial) fees shall be as follows:
Additional fee of 3% shall be added to all fees listed below for the Ohio Board of Building Standards | |||
Plan Examination | Processing Fee | Fee Per Hour |
Additional fee of 3% shall be added to all fees listed below for the Ohio Board of Building Standards | |||
Plan Examination | Processing Fee | Fee Per Hour | |
General plans | $100.00 | $100.00 | |
HVAC plans | $100.00 | $100.00 | |
Plumbing plans | $100.00 | $100.00 | |
Electrical plans | $100.00 | $100.00 | |
Automated sprinkler, other fire suppression systems, alarm systems, hoods, etc. | $100.00 | $100.00 | |
Industrial prefabrication, State- approved unit plans | $100.00 | $100.00 | |
System Permits | Processing Fee | Fee Per Hour | |
Base fee (for new and alteration building, plumbing, electrical, HVAC, and industrial, prefabrication permits only) | $200.00 | ||
Building permit (new, or addition, or alterations) | $250.00 | $10.00 per 100 sq. ft., $200.00 minimum | |
Electrical permit (new, additions, alterations) | $250.00 | $6.00 per 100 sq. ft., $100.00 minimum | |
Plumbing permit (new, additions, alterations) | $250.00 | $6.00 per 100 sq. ft., $100.00 minimum | |
HVAC (new, additions, alterations) | $250.00 | $6.00 per 100 sq. ft., $100.00 minimum | |
Industrial prefabrication, State- approved unit plans | $250.00 | $6.00 per 100 sq. ft., $100.00 minimum | |
Occupancy permit fee (if occupancy occurs prior to issuance of an occupancy permit, all occupancy permit fees and occupancy inspection fees shall be doubled.) | $6.00 per 100 sq. ft. (office space); $5.00 per 100 sq. ft. (other than office space); Maximum fee $4,000.00 | ||
Occupancy inspection fees (new, addition, alterations) | $200.00 | ||
Re-inspection fees (after first re- inspection) | $50.00 | ||
Miscellaneous Permits | |||
Demolition | $150.00 per story | ||
Building, moving hauling of heavy materials | $500.00 (300 sq. ft. or less of floor area); $1,000 (more than 300 sq. ft. of floor area) | ||
Elevator, lifts, cranes, derricks | $100.00 each | ||
Blasting permits | $100.00, plus actual cost of supervisory personnel | ||
Fee Per Hour | |||
Tanks for water, fuel, oil, gasoline or other flammables | Gallons | Fees | |
Under 3,000 | $100.00 | ||
3,000 to 11,999 | $200.00 | ||
12,000 to 19,999 | $300.00 | ||
20,000 to 49,999 | $400.00 | ||
50,000 to 99,999 | $500.00 | ||
Over 100,000 | $600.00 | ||
Interior or exterior swimming pool (public, commercial or nonresidential facility) | $200.00 | ||
Roofing | $5.00 per 100 sq. ft., $50.00 minimum | ||
Windows and doors | $50.00 per unit | ||
Exterior siding (more than 200 sq. ft.) | $50.00 | ||
Driveway (new, replacement, or repair over 10 sq. ft.) | $50.00 for first $1,000 value; $10.00 for each additional $1,000 value | ||
Parking lot (new, replacement, or repair/repaving over 10 sq. ft.) | $50.00 for first $1,000 value; $10.00 for each additional $1,000 value | ||
Site work (including clearing, grubbing, grading, drainage, etc.) | $100.00 for first $1,000 value; $10.00 for each additional $1,000 value | ||
New/Replacement Aprons | $100.00 | ||
Structures not otherwise identified | 0.005% of cost of construction | ||
(b) All fees listed above shall be based on the gross area of each story. When a building is not divided into stories, each section of 20 feet or part thereof of height shall be deemed a story. This provision shall not apply to roofs, attic spaces, roof appendages above the attic floor line and free-standing towers, elevators, chutes, theaters, halls, etc.
(c) The fee for a preliminary plan evaluation or a special evaluation of products and materials for the purpose of determining conditions acceptable for compliance with provisions of the Ohio Building Code shall be fifty dollars ($50.00) per hour.
(d) The fee for each special inspection other than those listed above shall be eighty dollars ($80.00) per inspection. Requests for special inspections shall be in writing to the Building Commissioner and the fee shall be paid prior to the inspection.
(e) Any person who fails to pay an inspection fee required for any inspection conducted by the Building Department for nonresidential structures, except for fees charged for the inspection of plans and specifications, within 45 days after the inspection is conducted, shall pay a late payment fee equal to 25% of the inspection fee.
(f) Before any such permit for moving any structure or building across or along any sidewalk, street, highway or public place is issued, it shall be approved by the Mayor or Chief of Police. Whenever it is deemed necessary in the public interest, the Mayor or Chief of Police may require that such moving operations be conducted under the supervision of such number of patrolmen as shall reasonably be required to safeguard life and property during the course of moving operations. A charge of sixty dollars ($60.00) per hour, per on-duty policeman, plus a charge of sixty dollars ($60.00) per hour, per police car, shall be made therefor. The officials issuing or approving such permits may prescribe, in writing, reasonable conditions, requirements, routes and precautions, and the day or days and hours of the day during which such moving operations shall be conducted as deemed necessary in the public interest, and all moving operations shall be performed in conformity therewith.
(Ord. 1986-25. Passed 4-9-86; Ord. 1988-23. Passed 3-9-88; Ord. 1998-138. Passed 11-11-98; Ord. 2008-149. Passed 8-13-08; Ord. 2010-105. Passed 11-10-10; Ord. 2014-12. Passed 1-8-14; Ord. 2014-59. Passed 4-9-14; Ord. 2014-90. Passed 8-13-14; Ord. 2015-5. Passed 1-14-15; Ord. 2015-101. Passed 12-9-15; Ord. 2016-08. Passed 1-5-16; Ord. 2016- 47. Passed 6-8-16; Ord. 2019-10. Passed 2-13-19; Ord. 2022-39. Passed 5-11-22; Ord. 2023-15. Passed 2-8-23; Ord. 2023-65. Passed 9-13-23.)