1327.10 FINAL INSPECTION.
The electrical contractor shall notify the Electrical Division when the entire installation of wiring and equipment has been completed, and it shall make inspection of the completed job within forty-eight hours, exclusive of Sundays and holidays, from such notification. If the complete installation shall pass inspection, the Electrical Division shall leave notice of such at the service equipment and notify the local electric and power company of the completion and approval of the job and authorize the connection to the installation, and no connections shall be made without such authorization. If the complete installation shall not pass inspection, the Inspector shall notify the electrical contractor of any violations, and the contractor shall correct any such violations within ten days from the date of written notice.
(Ord. 132-1968. Passed 9-23-68.)