1327.09 ROUGH INSPECTION.
The electrical contractor shall notify the Electrical Division as soon as the electrical wiring is to be lathed over or concealed and it shall make the inspection within forty-eight hours, excluding Sundays and holidays, from such notification. If the installation shall pass inspection, the Inspector shall stamp on the building permit the fact that he has passed the work. If the installation shall not pass inspection, the Inspector shall notify the electrical contractor of any violations and the contractor shall correct any such violations within ten days from the date of written notice.
(Ord. 132-1968. Passed 9-23-68.)