§ 53.53 DETAILED DESIGN (FINAL) DRAINAGE PLAN.
   (A)   The detailed drainage plan shall be incorporated into the secondary plat, as part of the construction drawings, or with a final site development plan. That submittal should be a finalized version of the earlier preliminary drainage plan.
   (B)   All final development and construction plans shall be submitted under the seal and signature of a professional engineer or professional land surveyor licensed to practice in the State of Indiana.
   (C)   Standard detail sheets. Standard detail sheets as adopted by the Crawfordsville Board of Public Works shall be included as part of the submittal.
   (D)   Required information. The City Engineer and Superintendent of Stormwater shall be empowered to require additional information to evaluate and determine the adequacy of the proposed stormwater facility.
   (E)   Certification required. All drainage plans submitted to the City Engineer, as described under this section, must be prepared by a registered professional engineer or registered professional land surveyor, licensed in the State of Indiana, and engaged in storm drainage design.
(Ord. 2-2010, passed 3-8-10)