All water main construction plans and specifications shall be reviewed and approved by the City Engineer. Prior to commencement of construction, the entity constructing the water main shall obtain a construction permit from the Nebraska Department of Health and Human Services after the water main construction plans and specifications have been approved as set forth above and before any water main construction work has commenced.
(Prior Code, § 52.057) Penalty, see § 52.999
(A) All workmanship and materials shall comply fully with the requirements of the approved plans and specifications. If at any time within one year after the date of the final inspection any defect shall appear which in the opinion of the City Engineer is due to inferior materials or workmanship, the property owner shall do whatever is necessary to remedy the defect at no cost to the city.
(B) The Director of Public Works or City Engineer will notify the property owner in writing of the defects and repairs to be made. If the party notified fails to commence repairs within ten days, the city may cause the defects to be remedied and charge the costs and expense involved to the property owner. The contractor surety shall not be relieved until the defects or repairs are corrected, approved and a written release is furnished to the surety by the city.
(Prior Code, § 52.059) Penalty, see § 52.999
Before any water main which is constructed by a private person or entity and connected to the city water system will be accepted and service commenced, the following requirements must be met.
(A) The water mains must pass all pressure tests required by either the Department of Public Works or the City Engineer.
(B) The water mains must pass all water quality tests required by the city and the Nebraska Department of Health and Human Services.
(C) The registered professional engineer licensed to practice in the State of Nebraska must inspect and approve the water main and issue a certificate of completion attesting that the water mains were constructed in accordance with the water main construction plans and specifications.
(D) The PW/ES Director and City Engineer must accept the engineer’s certificate of completion.
(E) Records must be presented to the City Engineer and Nebraska Department of Health and Human Services in hard copy format and an acceptable computer aided drafting format within 60 days of city acceptance of the project.
(Prior Code, § 52.061)