§ 1045.27 CONSTRUCTION ENTRANCES.
   Good housekeeping practices must be implemented to ensure sediment is not tracked off-site. Construction entrances shall be installed and maintained to minimize off-site tracking of sediments. A stone access drive should be installed at every point where vehicles enter or exit the site. Maintenance of the stone access drive with additional stone throughout construction to ensure mud is not tracked out onto the roadway is required. The length of the construction stone entrance must be at least 70 feet in length (30 feet for an individual sublot) and 14 feet in width.
(Ord. 15-O-2820, passed 5-19-2015)