Anyone issued a permit to occupy a street or sidewalk or an excavation and street cut permit shall adhere to the following specifications and requirements:
(a) If more than thirty percent (30%) of the cut or excavated street is impacted by the cut or excavation, then the street shall be resurfaced;
(b) If more than thirty percent (30%) of a cut or excavated lane is impacted by the cut or excavation, then the lane of a street shall be resurfaced;
(c) Paving will be block to block with "heel in” joints or if a shorter section is done, "heel in" joints will be provided ten (10) feet beyond the disturbance on each end; and
(d) All repairs (or parts thereof) shall be done in accordance with any further specifications adopted or required by the City Engineer or the Director of Public Works. (Ord. 22-17. Passed 10-6-22.)