1163.13 REVIEW PROCEDURE.
   Ten (10) copies of the completed application and Preliminary Development Plan shall be submitted to the Zoning Inspector at least sixteen (16) business days prior to the Planning Commission's next scheduled meeting. Failure to submit a complete application shall result in a refusal of acceptance. The Zoning Inspector shall transmit the complete application package to the Planning Commission and other parties as deemed appropriate for review and comment.
   A public hearing shall be held by the Planning Commission not more than sixty (60) days from the date of acceptance of the application package. The notification requirements for such hearing shall be as set forth in Section 1117.07.
(Ord. 27-11. Passed 3-14-11.)