§ 158.052 TENTATIVE APPROVAL.
   (A)   At its first regularly scheduled meeting after receipt of the village's consulting engineer's comments regarding the Preliminary PUD Plan, the Planning Commission shall review the Plan and shall make a recommendation to the Village Board regarding the Plan. In formulating its recommendations the Planning Commission shall make written findings as to each of the following issues:
      (1)   Whether the PUD will meet the use and density requirements of this chapter, including §§ 158.042 through 158.046.
      (2)   Whether the proposals for maintenance and conservation of the common open space are reliable.
      (3)   Whether the proposed planned unit development shall retain as much of the natural features of the site as is feasible including but not limited to:
         (a)   Existing trees.
         (b)   Natural water bodies.
         (c)   Steep slopes.
      (4)   Whether provision for public services, control over vehicular and pedestrian traffic, and the amenities of light and air, recreation, and visual enjoyment is adequate.
      (5)   In the case of a proposed planned unit development which contemplates construction over a period of years, whether the terms and conditions intended to protect the interest of the public and of the residents, occupants and owners of the proposed planned unit development in the total completion of the project are adequate.
      (6)   Whether the proposed planned unit development will not have an unreasonably adverse impact upon the area in which it is proposed to be established.
      (7)   Whether the proposed planned unit development is in accord with the general purposes of planned unit development set forth in this chapter.
   (B)   If upon meeting, the Planning Commission finds that the proposed Preliminary Plan and documentation satisfies the requirements of this chapter, the chairman of the Planning Commission shall certify the approval of the commission of the plan in substantially the following language:
The Preliminary Plan as shown herein is recommended for approval.
      Dated:______________________________
      By:________________________________
   (C)   No Preliminary Plan shall be approved by the Planning Commission unless there has been a prior review by the village's consulting engineer.
(Ord. 96-54, passed 3-26-96)