§ 158.046 PROCEDURE.
   (A)   The procedure for approval of PUDs consist of the following discrete steps in the following order:
      (1)   Pre-application conference (optional);
      (2)   Conceptual PUD Submission Plan;
      (3)   Preliminary PUD Plan;
      (4)   PUD Zoning Application;
      (5)   Plat/Plan Submission; and
      (6)   Construction Plan submission.
   (B)   In order to obtain a PUD zoning classification, the procedures set forth in this chapter must be followed step by step without variation or exception. When a PUD classification has been granted, the approved site plans and supporting documentation shall control use of land, regulate the spacing and height structures, control use of signs, and outline any deviations from the zoning and subdivision regulations of the village. Where no indication or exception is given to the zoning or subdivision regulations of the village, the requirements of the appropriate section of the zoning or subdivision regulations shall apply.
(Ord. 96-54, passed 3-26-96)