After the village’s consulting engineer informs the village that the following conditions have been met, the Subdivision Improvements shall be accepted by the village:
(A) The village’s consulting engineer has inspected the construction and all necessary repairs and corrections and certifies that the Subdivision Improvements required by this subchapter have been constructed.
(B) “As Built Plans” have been prepared by the subdivider’s engineer and delivered to the village’s consulting engineer.
(C) The village’s consulting engineer has received a signed statement of a registered professional engineer stating that the Subdivision Improvements have been observed during construction and installed to the specifications shown on the construction plans.
(D) The Subdivision Improvements, including but not limited to paved and un-paved drainage swales, detention facilities, and permanent erosion control measures, which are not to be dedicated to public use but which benefit the subdivision generally, have been built to specification shown in the construction plans.
(Ord. 94-01, passed 1-25-94; Am. Ord. 12-21, passed 6-12-12; Am. Ord. 16-35, passed 6-28-16)