§ 9-37 Approval and Costs of On-Site System.
   The owners of real estate obtaining a permit for water service shall submit plans for their on-site water distribution system, including on-site transmission lines to the City, for their review and approval before start of construction. All construction and non-construction costs of the on-site system are to be borne by the owners of real estate. During construction of said on-site water system the owners of real estate shall pay the expense of an inspector for the City and upon completion of construction, shall provide certified “as-built” construction drawings are not provided within three months after completion of construction, the City may prepare these drawings at the expense of the said owners of real estate. The City will provide the inspector, or may approve, in writing, some person designated by the owners of real estate to serve as the inspector. In any case, the owners of real estate will pay the cost thereof to the City who will, in turn, pay the inspector.
(`91 Code, § 9-37) (Ord. A-54, § 4.03 (h), 1-4-82)