§ 9-34 Oversizing and Reinforcing.
   Refunding of costs for oversizing to meet City specifications shall be made only as to that portion of the oversizing which lies within the real estate owners' development. Refunding of costs for reinforcing the City's existing water distribution system in order to provide adequate service to the development shall be determined by the Board of Public Works and Safety of the City. In the event the “availability contribution” per acre does not provide sufficient funds to extend and/or oversize the transmission line or to reinforce the existing system, as needed, no construction permit will be issued by the City unless the owners of real estate advance and pay the excess project costs.
(`91 Code, § 9-34) (Ord. A-54, § 4.03 (e), 1-4-82)