(a) Only closed loop geothermal well systems shall be allowed.
(b) At any time and for as long as a geothermal well system is in use, when a leak develops in the system, Carmel Utilities must be notified and an inspection made of the repairs.
(c) If a leak develops in the horizontal piping of a geothermal well system, it must be cut out and the system replaced. If the leak is in the vertical piping of the geothermal well, the well must be abandoned, and sealed.
(d) Carmel Utilities shall be notified of any intent to abandon any well and an inspection shall be made during the sealing procedure when abandoning any well.
(`91 Code, § 7-77) (Ord. A-62, § VI, 6-4-90; Ord. D-1663-04, 3-15-04)