922.17 APPLICATION PROCEDURES FOR STORM WATER POLLUTION PREVENTION PLAN.
   (a)   This plan will be combined with the Post-Construction Water Quality, Riparian Setback and Wetland Setback Plans that have also been developed for the site.
   (b)   Plans developed by the site owners and approved by the City in accordance with this regulation do not relieve the site owner of responsibility for obtaining and complying with all other necessary permits and/or approvals from Federal, State, county, and local agencies and departments. If requirements vary, the most stringent requirement shall be followed. Plans submitted to the City Engineer for review and approval, shall be accompanied by all other required permits and documentation relevant to the project, including but not limited to the permits required and issued by the U.S. Army Corps of Engineers, Ohio EPA and ODNR Division of Water.
   (c)   Three sets of the plans and necessary data required by this regulation shall be submitted to the City Engineer with text material being submitted on 8.5 by 11 inch paper and drawings on no larger than 24 by 36 inch sized paper. Submittals shall include:
      (1)   At the preliminary plan approval request, the preliminary plans only need to show all of the following existing and planned features: streams, water bodies, wetlands, riparian and wetland-setback areas, permanent BMPs and storm water management detention and retention basins.
      (2)   At the improvement plan approval request, the entire Comprehensive Storm Water Management Plan must be submitted.
   (d)   The City Engineer shall review the plans and shall approve or return these with comments and recommendations for revisions within 30 working days after receipt of the plan as described above. A plan rejected because of deficiencies shall receive a report stating specific problems. At the time of receipt of a revised plan, another 30 day review period shall begin.
   (e)   Approved plans shall remain valid for one year from the date of approval. After one year the plan(s) approval automatically expires.
   (f)   No soil disturbing activity shall begin before all necessary local, county, State and Federal permits have been granted to the owner or operator. Soil disturbing activities shall not begin and zoning permits shall not be issued without:
      (1)   Approved SWP3 or abbreviated SWP3;
      (2)   Installation of erosion and sediment controls; and
      (3)   Physical marking in the field of protected areas or critical areas, including wetlands and riparian areas.
   (g)   The City will do construction inspections until the site reaches final stabilization as determined by the City Engineer.
   (h)   The developer, engineer and contractor, and other principal parties, shall meet with the Building Department and/or his duly authorized representatives for a pre- construction meeting no less than seven days prior to soil-disturbing activity at the site to ensure that erosion and sediment control devices are properly installed, limits of disturbance and buffer areas are properly delineated and construction personnel are aware of such devices and areas. Pre-construction meetings for abbreviated SWP3s may be waived at the discretion of the Building Department.
(Ord. 10080-2017. Passed 6-20-17.)